Timeline (per TSC)

El Alto Weekly PlanMilestone





14-JunM0
Owner(s), List of requirements (per application, cross-applications); Project Impact (Test Only or Code Change), Dev/Test Company Engagement
21-JunM1
Content Freeze
28-Jun

DEV Sprint 1
11-Jul

Dev Sprint 1 & kick-off Test Sprint 1
18-Jul

DEV Sprint 2 - Test Sprint 1
25-Jul

DEV Sprint 2 - Test Spint 1
2-AugNo Code Freeze but RC0
Early Drop & Dev Sprint 3
9-Aug

Dev Sprint 3 - Test Sprint 2
15-AugCode FreezeEurope HolidayDev Sprint 3 - Test Sprint 2
22-Aug

Test Sprint 3
29-Aug

Test Completion/Stabilization - Branching El Alto (TBC)
5-Sep
US HolidayRelease preparation
12-SepSign-Off
Sign-Off

DCAEGEN2 Platform (HIGHEST and HIGH)

key summary type created updated due assignee reporter priority status resolution
Loading...
Refresh

DCAEGEN2 Service Components  (HIGHEST and HIGH)

key summary type created updated due assignee reporter priority status resolution
Loading...
Refresh

DCAEGEN2 Security Items

key summary type created updated due assignee reporter priority status resolution
Loading...
Refresh

DCAEGEN2 Backlogs (critical)

key summary type created updated due assignee reporter priority status resolution
Loading...
Refresh