Agenda
- Status and Stucks
- Technical Discussion
- Making the PTL Happy
Notes
- Status and Stucks
Current POMBA Dublin Stories (Logging Project) -
Current Code Inspections
- POMBA hourly healthcheck (CD deployment) - http://kibana.onap.info:5601/app/kibana#/dashboard/AWAtvpS63NTXK5mX2kuS
General Status
- Dublin
- Tasks to be closed off (just a technicality):
- Stories in progress: All 3 of them will be delivered by Feb-08.
- Stories to be formally verified before closure:
- - LOG-778Getting issue details... STATUS
- - LOG-763Getting issue details... STATUS
- - SDNC-475Getting issue details... STATUS : For network resource only and should be split into Network Discovery and ND context builder.
- - LOG-779Getting issue details... STATUS
- - LOG-404Getting issue details... STATUS
- Stories closed since last meeting:
- Bugs to enter:
- Latest security scan results show ~9 medium issues that should be recorded (but aren't severe enough to merit immediate work).
- Bugs entered in last week:
- Bugs in progress:
- Bugs to be verified:
- Bugs closed off since last meeting:
- Dublin
- Technical Discussion
- Note we need to be careful about breaking POMBA when in the middle of incremental updates, where OOM isn't yet done.
- Organizing Models and Swaggers between releases
- Basic navigation should take us to current
- It should also be possible to get Casablanca information
- Wiki needs some reorganization
- Consider demo schedules
- J. Ram Balasubramanian will forecast demos as development progresses
Data Dictionary & Network Discovery- Dec 20Done
- L2 Network data
- Let's demo with some rules.
- If we want validation run on new data, then Feb 21st makes more sense
- Additional enhancement - March 21st
- J. Ram Balasubramanian will forecast demos as development progresses
- Should ping the automation team on POMBA usage
- Chesla to ping Brian.
- Making the PTL Happy
- Dublin
- Should look at milestones and ensure we are in good shape.
- Feature commitment Jan 17 → pushed one week. Jan 24th. (M1)
- Prudence is supporting Michael for this activity.
https://wiki.onap.org/display/DW/Logging+Dublin+M1+Release+Planning
- Functionality freeze Feb 14
- Not sure if this was impacted by M1 slip - nope - still the 14th
- API freeze is March 14th.
- Feature commitment Jan 17 → pushed one week. Jan 24th. (M1)
- Should look at milestones and ensure we are in good shape.
- Dublin