Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 5 Current »

DRAFT PROPOSAL FOR COMMENTS

The following items are expected to be completed for the project to Pass  Release Sign-Off Milestone.

Release Sign-Off Milestone overview is available in wiki.


Practice AreaCheckpointYes/NoEvidencesHow to?
Product ManagementAre committed Product Backlog Stories been coded and marked as "Closed" in Jira?Yes

completed (52)

Getting issues...


Not completed (0)

Getting issues...  

 


Are all tasks associated with committed Product Backlog Stories been marked as "Closed" in Jira?YesLink to Jira
Provide the project features list under the form of a bulleted list.

New services - SNMP Trap Collector, HV-VES, DataFileCollector, PNF Registration Handler

DCAE Platform upgrades

  • TLS cert distribution
  • PNDA integration prep

Also specified under first section of the release notes: https://onap.readthedocs.io/en/casablanca/submodules/dcaegen2.git/docs/sections/release-notes.html


Summarize any functionalities that were planned at Release planning and not delivered at Release Sign-Off

Yes

VES-Mapper, Heartbeat, TCA-Gen2 and PM-Mapper were identified as Stretch goal for R3. They provide additional value to DCAE: supporting data format mapping (to VES), detection of missing heartbeat messages from xNFs, replaced to CDAP TCA and translation of 3gpp bulk file into measurement. These functions were not identified for ONAP R3 usecases and was listed as stretch goals due to resource and time constraints.

Except PM-Mapper, the other components have all delivered their docker container images, however the platform integration work and release compliance (sonar, csit, clm) work couldn't be addressed in time for Casablanca. The work on these would continue and targeted for Dublin.


Release ManagementHave all issues pertaining to FOSS been addressed?


Have all findings from previous milestones been addressed?YesProvide link to JIRA findings
DevelopmentAre all the Jenkins jobs successfully passed (verify + merge jobs)?Yeshttps://jenkins.onap.org/view/dcaegen2/
Are all binaries available in Nexus Release repository?Yes


Are all Docker images available In Nexus?YesProvide link to evidence
Are the Java and Docker manifest updated with the same version as in Nexus Release repository?Yes
Integration and Testing

Have all CSIT Use Cases (created by each project team) passed?No

HV-VES CSIT jobs failin; pending merge https://gerrit.onap.org/r/#/c/73226/1

https://jenkins.onap.org/view/dcagen2/

Goal is to incease our confidence the latest commit did not break the major functionality. Jenkins CSIT Jobs
Has the project code successfully passed the Daily Build process?Yeshttps://jenkins.onap.org/view/dcaegen2/Goal is to ensure the latest project commit has not broken the Integration Daily Build 

Has the project done the integration testing with related dependent projects?

YesCasablanca Release Integration Testing Status
Documentation

Has your team contributed and completed work in the following documentations in ReadTheDocs:

  1. Release Notes
  2. Project Documentation
Yes

https://onap.readthedocs.io/en/casablanca/submodules/dcaegen2.git/docs/sections/release-notes.html

https://onap.readthedocs.io/en/casablanca/submodules/dcaegen2.git/docs/index.html


Provide Link to ReadTheDocs Release Notes

Provide Link to ReadTheDocs Project Documentation





  • No labels