The following items are expected to be completed for the project to Pass the Release Candidate Milestone.

This template must be filled out for every Release Candidate Milestone (RC0, 1, 2, x)

RC Release Candidate Milestone overview is available in wiki.


Practice AreaCheckpointYes/NoEvidencesHow to?
Product ManagementAre all tasks associated with the release been marked as "Done" in Jira?Yes

Getting issues...



Have all findings from previous milestones been addressed?YesLink to Project backlog
DevelopmentHave all Defects of priority Highest and High been in status "Done" in Jira?

Yes

Getting issues...

Team is working on the ETAs and planning close them in next week.


Are all JIRA issues used as a reference in a commit in status "Done" in Jira?

Yes

Link to Project backlogVery often, some JIRA issue remains in status "Todo" in JIRA while the commit they are referenced to is successful.
Is there any pending commit related to Highest and High priority issues older than 36 hours in Gerrit? In case there are messages going back and forth between authors and reviewers, it is acceptable to be above 36 hours.No

https://gerrit.onap.org/r/#/q/status:open+projects:%22portal%22



Are all the Jenkins jobs successfully passed (verify + merge jobs)?Yeshttps://jenkins.onap.org/view/portal/

Has the team delivered all their release artifacts in Nexus Release or Nexus Staging repo?

There should be at least ONE version of each artifacts available in Nexus Release or Nexus Staging repo.

Yes

Portal-SDK artifacts version 2.4.0 are released. - https://nexus.onap.org/#nexus-search;quick~portal-sdk


Refer to Independent Versioning and Release Process for procedure
Integration and TestingHave all CSIT Use Cases (created by each project team) passed?

Yes

Jenkins External Labs


Is there a Docker images available for each repository?Yes

We use "latest" version for docker images for integration testing.

However, released 2.3.0 docker images


Has the project code successfully passed the Daily Build process?Yeshttps://jenkins.onap.org/view/portal/Goal is to ensure the latest project commit has not broken the Integration Daily Build 
Has the OOM deployment passed?

Yes

Ensure in Jenkins External Labs all Health Check pass

Windriver OOM Health check pass along with 16 new test cases passed - link (as of 24 Oct 2018)


Has the Heat deployment passed?Yes
Documentation

For RC0, for project delivering binaries, has the team populated and validated all the sections of either the Platform Component or SDK template?


Yeshttp://onap.readthedocs.io/en/latest/submodules/portal.git/docs/index.html

Most teams have already created the high level file structures in readthedocs, and populated some actual documentation. However, the remaining sections of the appropriate teamplate must be completed.

Platform: A&AI, APP-C, CLAMP, CLI, DCAE, DMaaP, Holmes, MSB, OOM, Policy, Portal, SDN-C SDC, SO, UseCase UI, VFC, VID

SDKs: AAF, CCSDK, External API Framework, Multi VIM/Cloud, VNFSDK

For RC1, has the team addressed any issue (recorded in JIRA) provided by the Documentation team?

Yes

http://onap.readthedocs.io/en/latest/submodules/portal.git/docs/index.html

Pairwise testing issues fixed - Portal Pair Wise Testing for Casablanca Release


For RC2, for project delivering binaries, has the team populated and validated all the sections of the Release Notestemplate?

Yes

For RC2, has the Documentation Team provided the final approval for your project documentation?In progress