This centralized page, for all Dublin projects, is aimed at identifying the risks as they are foreseen within the release life cycle.

A Risk that materialized becomes an Issue.

Status:

  • Identified: a risk that has been identified, but has not yet been analyzed / assessed yet 

  • Assessed: an identified risk which currently has no risk response plan 

  • Planned: an identified risk with a risk response plan

  • In-Process: a risk where the risk response is being executed 

  • Closed: a risk that occurred and is transferred to an issue or the risk was solved/avoided

  • Not occurred: a risk that was identified but that did not occur 

  • Rejected: created and kept for tracking purposes but considered not to be used yet







Risk ID

Project Team or person identifying the risk

Identification Date

Risk (Description and potential impact)

Team or component impacted by the risk

Mitigation Plan

(Action to prevent the risk to materialize)



Contingency Plan - Response Plan

(Action in case of the risk materialized)

Probability of occurrence (probability of the risk materialized)

High/Medium/Low

Impact

High/Medium/Low

Status

Risk ID

Project Team or person identifying the risk

Identification Date

Risk (Description and potential impact)

Team or component impacted by the risk

Mitigation Plan

(Action to prevent the risk to materialize)



Contingency Plan - Response Plan

(Action in case of the risk materialized)

Probability of occurrence (probability of the risk materialized)

High/Medium/Low

Impact

High/Medium/Low

Status

1

SDNC

1/14/19

NETCONF/TLS support is new in OpenDaylight Fluorine release. Thus, ONAP will be one of the early adopters and hence there is some element of risk.

SDNC/APPC

Some team members have conducted early testing of NETCONF/TLS and are working closely with the OpenDaylight community so that any defects can be addressed in Fluorine timeframe.

Fall back to NETCONF/SSH

Medium

Medium

Closed - we upgraded to Fluorine SR2 to pick up a fix that we needed for NETCONF/TLS. Other than that, testing has been successful and we did not need to fall back.

2

@Yuriy Malakov
@Alexis de Talhouët

1/15/19

PNF use case being dependent on the delivery of the 5G use case, if it doesn't get deliver, then we won't be able to showcase the E2E automation for the PNF use case in Dublin.

CCSDK
CDS
SO

We will provide support in discussions around E2E automation and help driving success of PNF use case.

Demonstrate the E2E automation functionality using VNF use case.

<Viable alternative?>

Medium/High (Scorecard for M2 still empty)

Low

Assessed

Closing as alternative exists and RC cycles not endangered

3

Portal

8 Jan 2019

Security impact on Policy, VID apps that use portal/sdk regarding addressing NexusIQ security issues and AAF integration which is not committed by Portal team so far due to lack of resources;

Policy, VID, AAF

Requesting open community for resources who can help with NexusIQ security critical issues in portal/sdk and portal.

Document the security impact in the release note

High

High

Assessed

4

Portal

8 Jan 2019

Impacts Dublin platform maturity requirements (Footprint Optimization, Logging Capabilities). Also, OOM deployment is impacted if the DB scaling changes are not supported by Portal team; also the changes for simplification of etc/hosts entries impacts the OOM deployment which is not committed by Portal team so far due to lack of resources.

OOM, Integration/Testing

Requesting open community for resources who can help with Footprint Optimization, Logging Capabilities in Portal under OOM scripts.

Risk partially addressed: @Michael O'Brien is helping to address the logging capabilities.

High

Medium

Assessed

5

CLAMP

23 Jan 2019

New policy api(and contents) for CRUD operations on policies not defined yet

CLAMP, Policy

use old policy API

create config. policy the old("R3 release") way

Low
(Policy team eventually committed so Risk can be closed)

Medium

Closed

6

CLAMP

23 Jan 2019

Blueprint generated by DCAE-D (SDC) might not be compatible with DCAE

CLAMP, DCAE-D, DCAE

Keep current manual blueprint onboarding in SDC (as VFI).

Manually created blueprint with correct format manually on boarded in SDC and distributed to CLAMP and DCAE.



High

Low

Closed

7

CLAMP

23 Jan 2019

New DCAE API to get status of µS not yet defined

CLAMP, DCAE

use current DCAE api

monitor only µS created by CLAMP

High

Low

Closed

8

AAF

24 Jan 2019

NOTE: This Comment is only referring to Stretch Goals. Our Committed work is proceeding apace.

Originating company has reduced available developers for AAF. New features cannot be guaranteed.

This applies ONLY to Stretch goal of CMPv2 (see #9) and request for Cookie Authentication (not listed here)

AAF

Dublin planning for AAF is conservative on new code commitments.



We have removed the Stretch Goals from our Commitment

Community Step-up

Not a Risk

Not a Risk

Closed

9

AAF

24 Jan 2019

This is a Stretch Goal. See #8, we don't have time or resources to accomplish in Dublin.

CMPv2 is asked for by VNFs, including Nokia

AAF/VNF

Few Resources. Existing Java Libraries not found.



We have removed the Stretch Goals from our Commitment

a) someone finds reliable CMPv2 libraries for Java

b) Write own from scratch

Not a Risk

Not a Risk

Closed

10

OOF

25 Jan 2019

Impact of the requirement of migrating to OOM based CSIT

OOF

Requesting the community for resources who can help with this ask for Dublin.

Provide prompt support to any issue that will be identified during the pair-wise testing and integration testing

High

Medium

Closed

(3/28 - based on expected contributions from IBM for CSIT)

 11

DCAE 

15-Feb-2019 

The new lifecycle Policy API definition being introduced for Dublin are under draft and having frequent churn; this is blocking DCAE Policy Handler evaluation/enhancement required to support this API. Based on current assessment of draft versions - new proposed updates impacts existing client (PH) handling of policy data in significant manner. Also its not clear if the old API's should be also supported by client in parallel, which adds more complexity.

DCAE, Policy, CLAMP

Requesting Policy team finalize the API definition soon in a way its not major rework for the clients.

Continue current (r3) api's

 High

 High

Closed

(3/12 - Based on discussion with Policy team, DCAE proceeding with new api implementation support)

12

Integration

14-Feb-2019

S3P- Geo-Redundancy - Lab Environment to be available by M4

Integration

Brought it up to TSC

Test Rancher clusters in Windriver lab

High

Medium

Assessed

13

Integration

19-Feb-2019

Resource has been identified and committed to the development of new cases/functional requirements/non-functional requirements, however new development work can and will break existing functionality and delays other team development and testing. There is few mechanism in place today to prevent it until the integration test time (which is too late)

Integration and all teams

Daily integration CI and add passing integration sanity test to milestone checklist

Enforce it at each milestone

Medium

Medium

Assessed



Integration sanity test has been added to milestone checklist. The remaining issue is to solve blocking issues quickly

14

Integration

20-Feb-2019

Windriver lab becomes the solely integration lab right now after TLab was out. Windriver lab is single point of failure for ONAP integration test, and any disturbance or resource shortage in Windriver lab would jeopardize Dublin release. We are already running into resource crunch in Windriver lab now.

Integration

Set up ONAP on Azure and experiment integration test on it (ONAP deployment and vFWCL)

Scale up to support full integration test on Azure in case of disruption or resource shortage in Windriver lab

High

High

Assessed



The current plan is to bring back TLab. No specific timeline is given

15

AAI

19-Feb-2019

AAI has a breaking change in the PNF object in Dublin. Request for feedback from all PTLs has been made, will assess based on feedback after next week's PTL call whether or not this can go in.

If the change goes in, data migration will need to happen for embedded PNFs, and AAI may be resource constrained in developing the migration utilities.

AAI, VID

Get confirmation from PTLs that the breaking change is OK



Do not accept the change in Dublin

Low

High

Being assessed

Closed 3/5, won't do in Dublin. Will add a release note to Dublin to warn implementors of the pending change in El Alto

16

OOM

20-Feb-2019

May not be able to deliver on Network Policies (OOM-1507) due to insufficient resources.

OOM

Need more resources

May be pushed to El Alto if unable to deliver within current release.

High

Low

Assessed

Moved to El Alto - closed

17

OOM

20-Feb-2019

Dublin Helm Charts not being deployed to public ONAP Helm repository.

OOM

Raised [ONAP Helpdesk #68891]

Working with LF now and should be resolved shortly. Once resolved will close this issue.

Low

Low

Assessed

Closed 2/28 as #68891 is resolved.

18

Model Driven Control Loop

25-Feb-2019

The work on the SDC TOSCA-Lab compliant models is progressing very slowly. Open questions for the SDC team regarding format of models and issues with current TOSCA-Lab are not getting answered. This is stretch goal for SDC, but is affecting the other projects team to fulfill their commitments.

Policy, DCAE, CLAMP

Requesting SDC to help with open questions.

May descope.

May need to push to El Alto.

Medium

High

Closed - resolved questions with SDC team.

19

DMaaP

25-Feb-2019

For Footprint Optimization requirement, the decision regarding Ubuntu vs. Alpine vs. something else needs to be solidified. Need to know the final outcome so that teams can focus on their implementation efforts.

DMaaP, all apps on Linux impacted by this requirement.

TSC to hold a meeting to discuss this further to arrive at a conclusion.

update - TSC held the meeting and decided to move further with Alpine for Dublin.

May need to push to El Alto

High

High

Closed

20

SDC

3-Mar-2019

May not be able to reach 55% test coverage due to insufficient resources

SDC

Asking the community to contribute as many tests as possible

Consulting TSC

Finish by RC2

High

Low

Being assessed

21

SDC

6-Mar-2019

May not be able to deliver a CSIT/OOM test

SDC

Asking the community to contribute such test

Consulting TSC

Move to El Alto

High

Low

Being assessed

22

CLAMP

8-Mar-2019

May not be able to deliver a CSIT/OOM test

CLAMP

Asking the community to contribute such test

Consulting TSC

Move to El Alto

Medium

Medium

Realized

(this risk is perceived as low impact to Dublin)

23

SO

11-Mar-2019

May not be able to deliver a CSIT/OOM test

SO

Asking the community to contribute such test

Consulting TSC

Move to El Alto

Medium

Medium

Being assessed

(Need to assess this risk - although perceived low impact to Dublin)

 24

 Scaling Use Case

Mar 19, 2019 

Since VNF Instantiation is not working now we are unable to get valid contents of AAI custom query which is blocking develop of Policy

Policy

Must be able to instantiate VNFs soon!



Investigate if we can continue to use named query

High

High

Closed (Instantiation finally works)

25

SDC

26-Mar-2019

Won't integrate with AAF and support HTTPS

SDC

Postponing to El Alto

Postponing to El Alto

High

Medium

Closed

26

MultiCloud

29-Mar-2019

Lack of resource to meet S3P/Security requirement for MultiCloud Azure plugin:

Docker Image footprint optimization,

Secured Communication.

MultiCloud Azure Plugin

Postponing to EI Alto

Postponing to EI Alto

High

Low

closed (not do in dublin)

27

SDC

1-Apr-2019

Might not be able to deliver CCVPN use case support in Dublin

CCVPN use case team

Raised the risk in SDC weekly

Postponing to EI Alto

Medium

Medium

Being assessed

Closing - move to future release

28

OOM

10-Apr-2019

Helm Chart transfer not complete

AAI, SO, Policy, Clamp, OOF

Allowed to complete migration post M4

Postponing to EI Alto

High

Medium

Action plan discussed (Helm xfers until RC0 - else move to El Alto)

Closed