Practice AreaCheckpointYes/NoEvidencesHow to?
Product ManagementAre all tasks associated with the release been marked as "Closed" in Jira?Yes

Issues




Have all findings from previous milestones been addressed?Yes(Note: in RC0, there were still troubles starting and health-checking in OOM. These have been resolved)
DevelopmentHave all Defects of priority Highest and High been in status "Closed" in Jira?Yes


Getting issues...


Are all JIRA issues used as a reference in a commit in status "Closed" in Jira?Yes

Getting issues...


Is there any pending commit related to Highest and High priority issues older than 36 hours in Gerrit? In case there are messages going back and forth between authors and reviewers, it is acceptable to be above 36 hours.No

Are all the Jenkins jobs successfully passed (verify + merge jobs)?Yes

https://jenkins.onap.org/view/aaf/

10-24- CSIT jobs working fine until this morning, will re-run


Has the team delivered all their release artifacts in Nexus Release repo?

There should be at least ONE version of each artifacts available in Nexus Release repo.

Yes

https://nexus.onap.org/#nexus-search;gav~org.onap.aaf.authz~~2.1.5~~


Refer to Independent Versioning and Release Process for procedure
Integration and TestingHave all CSIT Use Cases (created by each project team) passed?WIP

https://jenkins.onap.org/view/aaf/.


10/24 CSIT Burped this morning, with no changes posted. Investigating


At RC1, has the Pair Wise testing table been filled out?YesCasablanca Pair Wise Testing master page
At RC1, have all OOM Release Healtcheck related to your project passed?YES!

https://jenkins.onap.org/view/External%20Labs/


At RC1, is there a Docker image in Nexus Docker-Release repo available for each repository?Yes

https://nexus3.onap.org/service/rest/repository/browse/docker.release/v2/onap/aaf/

2.1.5 version released


Has the project code successfully passed the Daily Build process?Yeshttps://jenkins.onap.org/view/aaf/
Has the OOM deployment passed?Yes

http://onapci.org/grafana/d/8cGRqBOmz/daily-summary?panelId=8&fullscreen&orgId=1



Has the Heat deployment passed?

(not a gating item for Casablanca)

Yes

https://jenkins.onap.org/view/External%20Labs/



Documentation

For RC1, for project delivering binaries, has the team populated and validated all the sections of either the Platform Component or SDK template?


Yes

https://onap.readthedocs.io/en/latest/submodules/aaf/authz.git/docs/index.html

https://onap.readthedocs.io/en/latest/submodules/aaf/authz.git/docs/sections/release-notes.html

https://onap.readthedocs.io/en/latest/submodules/aaf/sms.git/docs/index.html

Most teams have already created the high level file structures in readthedocs, and populated some actual documentation. However, the remaining sections of the appropriate teamplate must be completed.

Platform: A&AI, APP-C, CLAMP, CLI, DCAE, DMaaP, Holmes, MSB, OOM, Policy, Portal, SDN-C SDC, SO, UseCase UI, VFC, VID

SDKs: AAF, CCSDK, External API Framework, Multi VIM/Cloud, VNFSDK

For RC1, has the team addressed any issue (recorded in JIRA) provided by the Documentation team?

Yes

For RC2, for project delivering binaries, has the team populated and validated all the sections of the Release Notestemplate?




For RC2, has the Documentation Team provided the final approval for your project documentation?