OOF Casablanca M3 API Freeze Milestone Checklist

The following items are expected to be completed for the project to Pass the M3 API Freeze Milestone.

M3 Release Architecture Milestone overview is available in wiki.

Usage

  1. Use the "Copy" and "Move" options (available under the ..., top right of this page) to duplicate this template into your project wiki.

  2. Fill out the Yes/No column

  3. Provide link to evidence (when necessary)

Practice Area

Checkpoint

Yes/No

Evidences

How to?

Practice Area

Checkpoint

Yes/No

Evidences

How to?

Architecture



Has the Project team reviewed the APIs with the Architecture Committee (ARC)?

Yes

https://lf-onap.atlassian.net/browse/ONAPARC-201

ARC Review Artifacts

Architecture walkthrough to understand how each project contributes on Release Use Case. ARC to organize the walkthrough.

Is there a plan to address the findings the API review?



Link to plan

The plan could be as simple as a Jira issue to track the implementation of findings or a documented plan within the wiki.

Does the team clearly understand that no changes in the API definition is allowed without formal TSC review and approval?

Yes

NA

In the case some changes are necessary, bring the request to the TSC for review and approval.

Is there any changes in the scope, functionalities, deliverable, dependency, resources, API, repositories since M1 milestone?

Yes

"Policy-based enhancements to capacity checks" proposed in M1, has been reduced in scope to implement only the Intent API (and exclude the intent-cost evaluation) - Edge Scoping MVP for Casablanca - ONAP Enhancements#ONAPEnhancements-ONAPEnhancements-Cloud-agnosticPlacement/Networking&HomingPolicies(Phase1-CasablancaMVP,Phase2-StretchGoal)



Provide link to the API Documentation.





https://onap.readthedocs.io/en/latest/submodules/optf/has.git/docs/sections/offeredapis.html

https://onap.readthedocs.io/en/latest/submodules/optf/osdf.git/docs/sections/offeredapis.html



Release Management

Are committed Sprint Backlog Stories been marked as "Done" in Jira board?

Yes

Getting issues...



Are all tasks associated with Sprint Backlog Stories been marked as "Done" in Jira?

Yes

Getting issues...



Have all findings from previous milestones been addressed?

NA

Provide link to JIRA findings



Development

Is there any pending commit request older than 36 Business hours in Gerrit?

No





Do you have a plan to address by M4 the Critical  and High vulnerabilities in the third party libraries used within your project?

NA

There are not identified security vulnerability for all repos

optf-has-Build-20180820-161135.pdf

optf-osdf-Build-20180820-161207.pdf

Ensure by M4 the Nexus-IQ report from “Jenkins CLM” shows 0 critical security vulnerability. Open the Nexus-IQ report for the details on each repo.

Are all the Jenkins jobs successfully passed ( Merge-Jobs)?

Yes

https://jenkins.onap.org/view/optf/



Are all binaries available in Nexus?

Yes

HAS: https://nexus.onap.org/content/repositories/snapshots/org/onap/optf/has/optf-has-conductor/1.2.0-SNAPSHOT/

OSDF: https://nexus.onap.org/content/repositories/snapshots/org/onap/optf/osdf/optf-osdf/1.2.0-SNAPSHOT/



Integration and Testing


Have 50 % of System Integration Testing Use Cases been implemented successfully in Jenkins?

Yes*

There are 35 functional test cases for the existing repo. (https://jenkins.onap.org/view/CSIT/)

Tests for the new repo (CMSO) are being added by the team.



Has the project code successfully passed the Daily Build process?

Yes

https://jenkins.onap.org/view/optf/job/optf-has-master-verify-java/

https://jenkins.onap.org/view/optf/job/optf-osdf-master-osdf-verify-java/

Goal is to ensure the latest project commit has not broken the Integration Daily Build