The following items are expected to be completed for the project to Pass the M4 Code Freeze Milestone.
M4 Release Code Freeze Milestone overview is available in wiki.
Practice Area | Checkpoint | Yes/No | Evidences |
---|---|---|---|
Product Management | Have all JIRA Stories supporting the release use case been implemented? | Yes | support for appc is in progress and working with AT&T to complete it by RC0. |
List the Stories that will not be implemented in this current Release. | Yes | All stories implemented. | |
Are committed Sprint Backlog Stories been coded and marked as "Done" in Jira? | Yes |
Getting issues...
| |
Are all tasks associated with committed Sprint Backlog Stories been marked as "Done" in Jira? | Yes | Getting issues... | |
Release Management | Have all issues pertaining to FOSS been addressed? | Yes | |
Have all findings from previous milestones been addressed? | Yes | No Specific findings. | |
Has the Project Team reviewed and understood the most recent license scan reports from the LF, for both (a) licenses within the codebase and (b) licenses for third-party build time dependencies? | Yes | ||
For both (a) and (b), have all high priority non-Project Licenses been either removed or escalated as likely exception requests? | Yes | ||
Development | Are all Defects of priority Highest and High in status "Done" in Jira? | Yes | Remaining High and Highest Defects : Getting issues... |
Has the project team reach the Automated Unit Test Code Coverage expectation? (Refer to artifacts available in Sonar) | Yes | Goal: 50% for Incubation project in Beijing is achieved : sonar link | |
Is there any binaries (jar, war, tar, gz, gzip, zip files) in Gerrit project repository? | No | ||
Is there any pending commit request older than 36 hours in Gerrit? | No | ||
Provide the "% Achived" on the CII Best Practices program. | 100% | ||
Is there any Critical level security vulnerabilities older than 60 days old in the third party libraries used within your project unaddressed? Nexus-IQ classifies level as the following:
which is complaint with CVSS V2.0 rating. | Yes | ||
Are all the Jenkins jobs successfully passed (verify + merge jobs)? | Yes | Jenkins CLI Tab | |
Are all snapshot binaries available in Nexus? | Yes | link to evidence | |
Do you have a clear plan to implement the Independent Versioning and Release Process by RC0? | Yes | ||
Integration and Testing | Have 100% of Continuous System Integration Testing (CSIT) Use Cases been implemented successfully in Jenkins? | Yes | |
Is there a Docker images available for your project deliverable? | Yes | Nexus 3 Docker repo | |
Has the project code successfully passed the Daily Build process? | Yes | Jenkins CLI Tab | |
Doc | Has the team created a docs folder and Development and Release Notes documentation templates in Readthedocs? | Yes | An updated Release note is ready in Read the docs, we still plan to further improve the release documentation in the coming weeks. |
Is the API documentation section populated? | Yes |