The following items are expected to be completed for the project to Pass the Release Candidate Milestone.

This template must be filled out for every Release Candidate Milestone (RC0, 1, 2, x)

RC Release Candidate Milestone overview is available in wiki.

Practice AreaCheckpointYes/NoEvidencesHow to?
Product ManagementAre all tasks associated with the release been marked as "Done" in Jira?

Getting issues... - These are all the Tasks marked as Closed and Resolved

Getting issues... - These are all the Tasks marked as NOT Closed or Unresolved




Have all findings from previous milestones been addressed?YesNo previous findings.
DevelopmentHave all Defects of priority Highest and High been in status "Done" in Jira?

Getting issues... - These are all the bugs of highest/high priority that are marked as Closed and Resolved

Getting issues... - These are all the bugs of highest/high priority that are NOT marked as Closed or Unresolved



Are all JIRA issues used as a reference in a commit in status "Done" in Jira?

Very often, some JIRA issue remains in status "Todo" in JIRA while the commit they are referenced to is successful.
Is there any pending commit related to Highest and High priority issues older than 36 hours in Gerrit? In case there are messages going back and forth between authors and reviewers, it is acceptable to be above 36 hours.
https://gerrit.onap.org/r/#/q/status:open+projects:policy
Are all the Jenkins jobs successfully passed (verify + merge jobs)?

https://jenkins.onap.org/view/policy/job/policy-common-master-verify-java/

https://jenkins.onap.org/view/policy/job/policy-common-master-merge-java/

https://jenkins.onap.org/view/policy/job/policy-drools-applications-master-verify-java/

https://jenkins.onap.org/view/policy/job/policy-drools-applications-master-merge-java/

https://jenkins.onap.org/view/policy/job/policy-engine-master-verify-java/

https://jenkins.onap.org/view/policy/job/policy-engine-master-merge-java/

https://jenkins.onap.org/view/policy/job/policy-drools-pdp-master-verify-java/

https://jenkins.onap.org/view/policy/job/policy-drools-pdp-master-merge-java/


Has the team delivered all their release artifacts in Nexus Releases repo?

There should be at least ONE version of each artifacts available in Nexus Releases repo.



Refer to Independent Versioning and Release Process for procedure
Integration and TestingHave all CSIT Use Cases (created by each project team) passed?
https://jenkins.onap.org/view/policy/job/policy-master-csit-health/
Is there a Docker images available for each repository?


Has the project code successfully passed the Daily Build process?

Goal is to ensure the latest project commit has not broken the Integration Daily Build 
Documentation

For RC0, for project delivering binaries, has the team populated and validated all the sections of either the Platform Component or SDK template?


n/a


Most teams have already created the high level file structures in readthedocs, and populated some actual documentation. However, the remaining sections of the appropriate teamplate must be completed.

Platform: A&AI, APP-C, CLAMP, CLI, DCAE, DMaaP, Holmes, MSB, OOM, Policy, Portal, SDN-C SDC, SO, UseCase UI, VFC, VID

SDKs: AAF, CCSDK, External API Framework, Multi VIM/Cloud, VNFSDK

For RC1, has the team addressed any issue (recorded in JIRA) provided by the Documentation team?

http://onap.readthedocs.io/en/latest/submodules/policy/engine.git/docs/index.html


For RC2, for project delivering binaries, has the team populated and validated all the sections of the Release Notestemplate?n/a

For RC2, has the Documentation Team provided the final approval for your project documentation?n/a