The following items are expected to be completed for the project to Pass the M3 API Freeze Milestone.
M3 Release Architecture Milestone overview is available in wiki.
Usage
- Use the "Copy" and "Move" options (available under the ..., top right of this page) to duplicate this template into your project wiki.
- Fill out the Yes/No column
- Provide link to evidence (when necessary)
Practice Area | Checkpoint | Yes/No | Evidences | How to? |
---|---|---|---|---|
Architecture | Has the Project team reviewed the APIs with the Architecture Committee (ARC)? | Yes | APPC Presentation | Architecture walkthrough to understand how each project contributes on Release Use Case. ARC to organize the walkthrough. |
Is there a plan to address the findings the API review? | N/A | See Note | Note: There were no findings coming out of the API review meeting; however, there is an item being addressed between MultiVIM and CDP-PAL around https support that needs to be resolved. CDP-PAL uses https, MultiVIM currently does not support it - both teams investigating to determine which solution would be most feasible in the short time we have. | |
Does the team clearly understand that no changes in the API definition is allowed without formal TSC review and approval? | Yes | NA | In the case some changes are necessary, bring the request to the TSC for review and approval. | |
Is there any changes in the scope, functionalities, deliverable, dependency, resources, API, repositories since M1 milestone? | Yes | If Yes, please a link to the evidence of these changes. | Two key items have increased the scope from what was understood at M1: | |
Provide link to the API Documentation. | In-Progress | Document is available and updated, will be posted by end of week | ||
Release Management | Are committed Sprint Backlog Stories been marked as "Done" in Jira board? | Yes | Provide Link to Project backlog | |
Are all tasks associated with Sprint Backlog Stories been marked as "Done" in Jira? | Yes | APPC JIRA Board | ||
Have all findings from previous milestones been addressed? | Yes | Provide link to JIRA findings | ||
Development | Has the project team reach the Automated Unit Test Code Coverage expectation? (Refer to artifacts available in Sonar) | No, work In-Pogress | Goal: 30-50% for Incubation project | Guidance on Code Coverage and Static Code Analysis |
Is there any pending commit request older than 36 Business hours in Gerrit? | No | |||
Are all the Jenkins jobs successfully passed ( Merge-Jobs)? | Yes | Provide link to evidence | APPC Gerrit | |
Are all binaries available in Nexus? | Yes | Provide link to evidence | APPC Snapshot on Nexus | |
Integration and Testing | Have 50 % of System Integration Testing Use Cases been implemented successfully in Jenkins? | No. In Progress | Provide link to evidence | APPC-104 |
Has the project code successfully passed the Daily Build process? | Yes | Goal is to ensure the latest project commit has not broken the Integration Daily Build |