Release Schedule
Approved by the TSC on August 26, 2021 (r5)
Activity Log
Date | Event or Update | Milestones Affected |
---|---|---|
Aug 26 | TSC approved one week slip to M3. No other milestones affected. | M3 |
Jun 23 | M2 approved by TSC, with exceptions, by email vote. | M2 |
May 20 | M1 approved by TSC, with exceptions. Details here. | M1 |
May 10 | Added ONESummit dates to the schedule (r4) for reference. (No changes to Istanbul release milestones from r3) | None |
May 6 | Approved by the TSC (r3) | ALL |
May 4 | New proposal (r3) in response to feedback at May 3 PTL meeting
| RC0, RC1, RC2 |
Apr 28 | New proposal (r2) in response to feedback from original proposal. | M1 - Sign Off |
Mar 18 | Proposal presentation to TSC. Requested approval of just the kickoff date of April 1. Other milestones to be discussed at a later date. TSC approved kickoff date ONLY. | M0 |
Mar 11 | Proposal presentation to TSC. TSC expressed concerns about the second half of the release occurring during the summer, which could conflict with summer holidays. Proposal not approved. | ALL |
Mar 10 | Second draft |
|
Mar 4 | Initial draft posted | N/A |