Since Usecase UI had request to be merged after M3, we submitted the request to OOM. But OOM thought it was too late after M3, so we decided to postpone the merge date of UUI NLP which was a new module of UUI and still had several problems. So we abandoned the commit request of UUI NLP and asked the OOM team wether the rest part of UUI module could be merged into H release
Schedule impact
N/A
Recovery plan
We abandoned the UUI NLP module and requested for merging again
Milestone schedule change
If not approved, the release plan of UUI module will postpone to next release