Honolulu Exception Request for Usecase UI





Name

@xu ran

Milestone or Requirements Exception?

Milestone

Project or Requirement Name and JIRA

Usecase UI



Milestones affected

RC0



Projects affected

Usecase UI

Background description

According to this Jira: USECASEUI-545: Start OOM review with updated container imageClosed, Usecase UI team thought the deadline of committing the functional codes was RC0 because there was nothing about configuration to be updated, but OOM team thought it was too late because the deadline of merging functional codes should be M3, and also the new UUI NLP module had several problems, so we decided to postpone the merge date of UUI NLP, abandon the commit request of UUI NLP and ask the OOM team wether the rest part of UUI module could be merged into H release

Schedule impact

N/A



Recovery plan

Abandon the UUI NLP module and request for merging again

Milestone schedule change

If not approved, the release plan of UUI module will be postponed to next release

Risk

N/A

Status

Closed

Decision

Approved: See- https://lf-onap.atlassian.net/wiki/x/QzXs