Sub-components are repositories are consolidate in a single centralized place. Edit the Release Components name for your project in the centralized page.
...
Risk identified | Mitigation Plan | Contingency Plan | ||
---|---|---|---|---|
To fill out | To fill out | To fill outcode to be scrubbed for release to ONAP | additional resources assigned | include in Beijing release |
Resources
Fill out the Resources Committed to the Release centralized page.
Release Milestone
The milestones are defined at the Release Level and all the supporting project agreed to comply with these dates.
...
It is not expected to have a detailed project plan.
Date | Project | Deliverable | To fill out | To fill out | To fill out|
---|---|---|---|---|---|
5/4/17 | M0 | Kickoff | |||
6/29/17 | M1 | Planning process Complete | |||
8/3/17 | M2 | Functionality Freeze | |||
8/24/17 | M3 | API/Data Model Freeze | |||
8/31/17 | Sprint 1 | sprint-1 created | |||
9/14/17 | M4 Sprint 2 | Code Freeze Sprint 1 complete, Sprint 2 created | |||
9/28/17 | RC0 Sprint 3 | Release Candidate 0 Sprint 2 complete, Sprint 3 created | |||
10/12/17 | RC1 Sprint 4 | Release Candidiate 1 Sprint 3 complete, Sprint 4 created | |||
10/26/17 | RC2 Sprint 5 | Release Candidiate 2 Sprint 4 complete, Sprint 5 created | |||
11/2/17 | Release Delivery | Target Release Date |
Documentation, Training
- Highlight the team contributions to the specific document related to he project (Config guide, installation guide...).
- Highlight the team contributions to the overall Release Documentation and training asset
- High level list of documentation, training and tutorials necessary to understand the release capabilities, configuration and operation.
- Documentation includes items such as:
- Installation instructions
- Configuration instructions
- Developer guide
- End User guide
- Admin guide
- ...
...
Each project must edit its project table available at FOSS VNF SDK.
Charter Compliance
The project team comply with the ONAP Charter.