Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Sub-components are repositories are consolidate in a single centralized place. Edit the Release Components name for your project in the centralized page.

...

  • VNF SDK: Develop
  • VNF Requirement: responsible for documenting VNF guidelines and requirements. It will produce requirements documents

Architecture

High level architecture diagram

At that stage within the Release, the team is expected to provide more Architecture details describing how the functional modules are interacting.

Block and sequence diagrams showing relation within the project as well as relation with external components are expected.

Anyone reading this section should have a good understanding of all the interacting modules.


Image Added


Image Added

Third Party Products Dependencies

...

Risk identifiedMitigation PlanContingency Plan
To fill outTo fill outTo fill outcode to be scrubbed for release to ONAPadditional resources assignedinclude in Beijing release

Resources

Fill out the Resources Committed to the Release centralized page.

Release Milestone

The milestones are defined at the Release Level and all the supporting project agreed to comply with these dates.

...

It is not expected to have a detailed project plan.

DateProjectDeliverable
To fill outTo fill outTo fill out5/4/17M0Kickoff
6/29/17M1Planning process Complete
8/3/17M2Functionality Freeze
8/24/17M3API/Data Model Freeze
8/31/17Sprint 1sprint-1 created
9/14/17

M4

Sprint 2

Code Freeze

Sprint 1 complete, Sprint 2 created

9/28/17

RC0

Sprint 3

Release Candidate 0

Sprint 2 complete, Sprint 3 created

10/12/17

RC1

Sprint 4

Release Candidiate 1

Sprint 3 complete, Sprint 4 created

10/26/17

RC2

Sprint 5

Release Candidiate 2

Sprint 4 complete, Sprint 5 created

11/2/17Release DeliveryTarget Release Date

Documentation, Training

  • Highlight the team contributions to the specific document related to he project (Config guide, installation guide...).
  • Highlight the team contributions to the overall Release Documentation and training asset
  • High level list of documentation, training and tutorials necessary to understand the release capabilities, configuration and operation.
  • Documentation includes items such as:
    • Installation instructions
    • Configuration instructions
    • Developer guide
    • End User guide
    • Admin guide
    • ...

...

Each project must edit its project table available at FOSS VNF SDK.


Charter Compliance

The project team comply with the ONAP Charter.