Duration 90 minutes - https://zoom.us/j/661303200

@4pm CET/10am EST/7am PST/10pm China Time/7.30pm India Time

...

Agenda ItemsPresented ByTimeNotes/LinksJIRA Tasks

Dublin Release

RC2 Follow-up

Sign-Off?

30
40 mins

Milestone Status 

  • Projects: Project Status in Dublin Release
  • RC2 status
    • 100% green for RC2 checklists
    • a few pair-wise tests still in process (passing %: 89% SO; 78% Policy)
    • RC2 TSC Recommendations -  RC2 GO - Approved by TSC - Congrats Team !
  • Sign-Off status
    • 29 projects (excluding Doc) 
      • 9 out of 29 are completed
      • 7 out of 29 are reporting with issues
      • 13 out of 29 have no reports
    • Sign-Off TSC Recommendations -  NO GO 
    • TODOs
      1. Continue rapid find/fix cycle
      2. Complete 7day stability tests
      3. Assess all requirements for testing completion and determine IN/OUT status for each
      4. Release notes, security docs, and other documentation
      5. Communicate our best guess schedule

Release Details

xx
      • 21 out of 34 are completed (including N/A)
xx
      • 4 out of 34 are at >=80% test completion
xx
      • 9 out of 34 <80% test completion
    • Review all RED status (evaluate for removal from release)
      • #3 – 60% vCPE
wioth
      • with TOSCA - drop from release
?
      • - Candidate to be descoped (Ypan to confirm by 6/7 EOD)
      • #8 - 68% PNF Pre-onboarding - probably completed (Ben to confirm by 6/7 EOD)
      • #10 80% Scale Out - Require 2 days and integration with CDS (Scott to provide feedback on PTL call 6/10)
      • #11 74% CCVPN - Lab issues - scope change (Seshu to provide an update of the content to the LF Mkt Team + Readthedoc)
      • #18 60% & 20% BBS -proposition to phase it - PH1 Completed. PH2 Blocked by issues in SO & SDNC.(David to provide PH2 feedback on PTL call 6/10)
      • #23 50% Consistent ID of a cloud Region - SO issue (Bin to provide  feedback on PTL call 6/10)
      • #25, #33 - no update
      • #30, 31 - Security & Magnus to follow-up
      • #34 - Ypan to follow-up
  • Documentation Tickets: Documentation Status for Dublin
Projects: Project Status in
  • Dublin
Release
  • 29 projects (excluding Doc) - Sign-Off
    • xx out of 29 are completed
    • xx out of 29 are in progress - blockers and/or documentation
  • Dublin
    • release branch NOT created – Long list to the right.... except Documentation since 5/15 (so cherry-pick)
  • RC2 TSC Recommendations -  RC2 GO or NO GO (with conditions)
  • Sign-Off TSC Recommendations -  GO or NO GO 
  •       JIRA Query - Remaining

    xxx

    526 Items

    status != Closed AND status != Done AND project != "Sandbox Project" AND project != CI-Management AND project != "ONAP TSC" and fixVersion = "Dublin Release" ORDER BY key ASC, priority DESC, updated DESC

    aaf/authz
    aaf/cadi
    aaf/luaplugin
    aaf/sms
    aaf/sshsm
    aai/eis
    aai/enricher
    aai/gap
    aai/tabular-data-service
    aai/test-config
    ccsdk/platform/blueprints
    ccsdk/storage/esaas
    dcaegen2/analytics/flink
    dcaegen2/analytics/pnda
    dcaegen2/analytics/tca-gen2
    dcaegen2/platform/cdapbroker
    dcaegen2/platform/servicechange-handler
    doc/tools
    externalapi/nbi
    holmes/common
    holmes/engine-management
    holmes/rule-management
    integration/benchmark
    integration/devtool
    integration/seccom
    logging-analytics/pomba
    modeling/genericparser
    modeling/toscaparsers
    msb/apigateway
    msb/discovery
    msb/java-sdk
    msb/service-mesh
    msb/swagger-sdk
    multicloud/azure
    multicloud/framework
    multicloud/k8s
    multicloud/openstack/vmware
    multicloud/openstack/windriver
    music/distributed-kv-store
    music/mdbc
    music/prom
    oom
    oom/offline-installer
    oom/registrator
    oparent
    oparent/cia
    optf/fgps
    portal
    portal/sdk
    sdc/sdc-be-common
    sdnc/adaptors
    testsuite/properties
    university
    vnfsdk/dovetail-integration
    vnfsdk/model

    Any Infrastructure Improvement/PlanLinux Foundation5 mins

    Global-jjb update - 11 of 29 projects complete!

    • Post-Dublin automation of info.yaml/LDAP (don't disrupt the release)

    Dockerhub migration - proposed start 2019-07-22 

    • Will update at PTL call (post-DDF)

    Contributor License Agreements (CLA)

    • Enforcement of CLAs will start on July 1. 
    • Information sent to the contacts from all companies that have contributed code to Dublin
    • Commits will be blocked if companies do not have a CLA in place

    Any LF showstopper

    Open

    #76359: Need help with the info.Yaml change

    Completed

    #76345: Please help release Usecase-UI repos for Dublin Release

    #76359: Need help with the info.Yaml change


    PTL Update - Integration10 mins

    In ODL, for instance, during release time-frame a few folks are granted “Supercommitter” rights, empowering them with merge rights on all repos. That way, when version number changes, or bug fix validated but no one to merge, etc., these set of people can take care of merging the needed patches and getting the release forward. Given our current structure in ONAP, where the integration team as to “vouch” for the state of ONAP before its release, it could make sense having Integration’s committer given such right.

    Suggestion: Integration Committers - 1 in APAC, 1 in EMEA & 1 in NAR to cover all the time-zones

    Scope: Code and Documentation

    Successful Story with OOM

    Alexis/Brian will prepare a detailed proposition to be reviewed by TSC

    Carried forward from May 30
    PTL Update - Portal5 mins
    Request for a TSC Confirmation vote on 

    Congratulations Lorraine Welch !

    Portal Committer Promotion Requests for Lorraine Welch


    Subcommittee Update - CVC
    15
    30 mins

    Alignment to El Alto

    View file
    name

    OPNFV Prioritized Deliverables 2019 v0.2

    VNF_Validation_MVP_for_ONAP_TSC_May-30-2019.pdf
    height150

    Carried forward from May 30
    Frankfurt Release
    10 min
    5 mins

    Frankfurt Activity's plan proposal from M0 to M1

    ONAP_Frankfurt_M0_M1_Proposal_V1.xlsx

    Carried forward from May 30

    Jira Legacy
    serverSystem Jira
    columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
    serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
    keyTSC-129

    TCC Update

    TSC Activities and Deadlines
    Congratulations to Alla Goldner being elected as our ONAP Strategic Planning Committee (SPC) representative
    Incoming ONAP Events5 mins

    Any remaining open question?

  • Decision on Nov 18th, 2019 for next ONAP DDF Event
  • ...

    • Fall DDF dates have been approved by the TSC:  Nov 19 - 22. The LF will begin working on a location. Companies with facilities in geo-politically neutral countries that are interested in hosting should contact Kenny Paul



    ...

    Zoom Chat Log 
    Anchor
    zoom
    zoom

    06:52:06 From Kenny Paul (LFN) : #topic rollcall
    06:55:46 From Catherine Lefevre : #info, Catherine Lefevre, ONAP TSC
    06:57:47 From Timo Perala (Nokia) : #info Timo Perala, Nokia
    06:57:53 From Andreas Geissler (Deutsche Telekom) : #info Andreas Geissler (DT)
    06:59:47 From Achilles De Villa : #info Achilles Devilla, Reliance Jio, proxy Ning So
    06:59:57 From Eric Debeau : #info Eric Debeau, Orange
    07:00:21 From Ciaran Johnston : #info Ciaran Johnston, Ericsson, proxy Stephen Terrill
    07:00:41 From ALLAGO : #info Alla Goldner, Amdocs
    07:00:46 From Adrian O'Sullivan : #info Adrian O’Sullivan, Huawei, proxy Chaker
    07:01:04 From bin.yang@windriver.com : #info Bin Yang, Wind River
    07:01:41 From Alexis de Talhouët : #info, Alexis de Talhouët, Bell Canada
    07:02:43 From Viswa ( Verizon ) : #info Viswa, Verizon
    07:03:31 From Jason Hunt : #info Jason Hunt, IBM
    07:04:46 From Milind Jalwadi : #info Milind Jalwadi, TechMahindra
    07:04:54 From Kenny Paul (LFN) : #topic Dublin Release
    07:05:13 From Yipan Deng (Intel) : #info proxy Yipan Deng, Intel Corp. (Proxy for Srinivasa Addepalli)
    07:05:18 From Catherine Lefevre : Congrats MUSIC Team !
    07:05:23 From Bharath Balasubramanian : Thanks!
    07:05:59 From Davide Cherubini : #info Davide Cherubini, Vodafone
    07:06:32 From Kenny Paul (LFN) : @Jim recommends RC2 is complete
    07:07:22 From Kenny Paul (LFN) : #AGREED The TSC approves RC2 as complete
    07:08:36 From Kenny Paul (LFN) : - Sign off on the release not ready
    07:09:35 From Kenny Paul (LFN) : - please remember to release a new image to integration after making a bug fix
    07:10:18 From Kenny Paul (LFN) : -SECCOM still waiting on 6 project updates
    07:10:57 From Kenny Paul (LFN) : -Integration blockers
    07:12:28 From Kenny Paul (LFN) : #ACTION @Yipan to follow up on OPTFRA-512 Due tomorrow
    07:16:18 From Kenny Paul (LFN) : -Integration status
    07:17:56 From Kenny Paul (LFN) : --vCPW w/ TOSCA @Yipan says that this should be moved to El Alto.
    07:18:20 From Kenny Paul (LFN) : #ACTION @Yipan to follow up on this tomorrow.
    07:18:28 From Lingli : #info Lingli, CMCC
    07:20:15 From Kenny Paul (LFN) : --5G PFN pre-onboarding
    07:21:43 From Kenny Paul (LFN) : @Ben @Brian - do not believe this is a blocker
    07:22:06 From Kenny Paul (LFN) : #ACTION @Ben follow up due tomorrow
    07:23:17 From Kenny Paul (LFN) : --Scaleout
    07:24:44 From Kenny Paul (LFN) : --- @Yuiry believe it is working - testing still needed
    07:26:05 From Kenny Paul (LFN) : #ACTION @ScottB will report on status at PTL meeting
    07:26:16 From Kenny Paul (LFN) : --CCVPN
    07:28:01 From Kenny Paul (LFN) : #ACTION @Seshu will follow up tomorrow
    07:29:09 From Kenny Paul (LFN) : --BBS
    07:31:50 From Eric Debeau : #info we tested end to end service deletion and it is working for vfw use-case
    07:31:59 From Kenny Paul (LFN) : @David P-C phase 2 - E@E service termination can probably be pushed to El Alto
    07:32:48 From Kenny Paul (LFN) : -difference may be the use of PNF resources
    07:33:26 From Kenny Paul (LFN) : #ACTION @David to follow up @ PTL meeting
    07:35:16 From Kenny Paul (LFN) : --consistent ID cloud region
    07:35:40 From Kenny Paul (LFN) : #ACTION @Bin to follow up at PTL meeting
    07:36:01 From Kenny Paul (LFN) : -SO-1995 needs to be added to the list.
    07:37:32 From Kenny Paul (LFN) : --SOL004 package security
    07:38:40 From Kenny Paul (LFN) : #ACTION @Ciaran to follow up
    07:39:22 From Kenny Paul (LFN) : --HPA vsec
    07:39:37 From Kenny Paul (LFN) : #ACTION @Yipan to follow upo
    07:40:55 From Kenny Paul (LFN) : --Please cut your Dublin Branches!!!
    07:43:53 From Kenny Paul (LFN) : #topic Infrastructure / RelEng
    07:44:23 From Kenny Paul (LFN) : --reminder global-jjb due July 19
    07:45:10 From Kenny Paul (LFN) : --CLAs take effect July 1
    07:45:33 From Kenny Paul (LFN) : #topic supercommitters
    07:46:17 From Kenny Paul (LFN) : -OOM supercommitter working well
    07:48:53 From Keong : would supercommitters be elected?
    07:51:58 From Kenny Paul (LFN) : -discussion of how to measure success,
    07:52:25 From Kenny Paul (LFN) : -@Mike E says this has been extremely helpful.
    07:54:01 From Kenny Paul (LFN) : -several suggestions of a trial
    07:54:35 From Keong : can the teams be more geographically distributed for better timezone coverage?
    07:55:02 From Eric Debeau : #info ok for the supercommitter proposal
    07:58:20 From Keong : do supercommitters need to meet the normal committer criteria as well?
    08:00:36 From Kenny Paul (LFN) : #ACTION @Alexis and @Brian F to put together a formal proposal at next week's TSC meeting
    08:02:26 From Manoop Talasila - AT&T : #TSC thanks for Lorraine’s approval
    08:02:44 From Brian : who is zoom htip ? cant seem to reply to them
    08:03:29 From Sai seshu : Sorry that's me Seshu... :)... Brian
    08:03:55 From Kenny Paul (LFN) : #topic VNF Validation
    08:04:05 From Sai seshu : It's the common zoom login that we use that pops up
    08:04:17 From Kenny Paul (LFN) : @Lincoln reviewed the slides attached to the minutes
    08:07:37 From Kenny Paul (LFN) : -discussion of alignment of the ONAP VVP program
    08:08:13 From Steven Wright : ONAP VVP project is different - this is LFN OVP ...
    08:09:01 From Viswa : Which program OVP or VVP provides the certification for ONAP-Compliant VNF ?
    08:09:25 From Kenny Paul (LFN) : -VNFRQTS and VVP are feeders to the OVP
    08:09:51 From Viswa : When a SP import a VSP in SDC, which program kicks in to verify the certification of VSP ?
    08:10:40 From Kenny Paul (LFN) : -Technical communitys still define the criteria
    08:13:14 From Steven Wright : If anyne has input in requirments for VNF certification, then please contribute to VNFRQTS
    08:13:26 From Eric Debeau : #info Heather presented OVP during the last ONS
    08:14:37 From Steven Wright : If you are interested to write tests for VNF packages - please contribute to VVP or VNFSDK as these will fold into the LFN OVP
    08:14:45 From Adrian OSullivan a00252210 : agree with Catherine, I'd like to see how ONAP and other LFN projects fit in with OVP and CVC, what is the hierarchy
    08:16:11 From Viswa : Same question in different way : If a vendor ask us where to go to get their VNFs ONAP-Certified, where should we guide them? VVP or OVP ?
    08:17:35 From Eric Debeau : #info https://www.lfnetworking.org/wp-content/uploads/sites/55/2019/04/OPNFV_ONAP_OVP_Web_040319.pdf
    08:17:57 From Steven Wright : @viswa, ONAP VVP provides tests for a VNF's HEAT template, but does not issue a certificate or logo. LFN OVP provides a process to otain a logo
    08:20:34 From Viswa : @Steven Thanks. So answer to my question is OVP ?
    08:21:49 From Brian : Linkage between OVP and ONAP needs to be improved since two things will happen 1) ONAP code will be used to test VNFs that operators care about and the OVP team doesnt really talk to integration team and 2) it really should be an ONAP validated VNF not an OVP validate VNF
    08:27:43 From Eric Debeau : @Brian. THe link is there as OVP is based on VVP and VNFSDK tools.
    08:29:12 From Brian : @Eric - ONAP team has been running the tests on VNFs so not clear how OVP team is working with the rest of ONAP since they will be moving into "instantiation" tests using an instance of ONAP somewhere as part of the next phase validation
    08:31:52 From Eric Debeau : Today, OVP is only focusing on a MVP testing the VNF descriptor. I agree that for next phases, we need more relationships.
    08:31:56 From Alexander Vul : The intent of ETSI NFV standards was to converge on a set of normative APIs, data formats, and packaging in order to optimize the automation story both from developer and operator perspective
    08:33:03 From Alexander Vul : We now seem to be undoing this, by proliferating different packaging formats and different VNF descriptor encodings...
    08:33:25 From Eric Debeau : The intent of ONAP is to converge on an open automation platform based
    08:33:42 From Alexander Vul : @Eric - Orange is leading most of this standardization in ETSI
    08:33:55 From Eric Debeau : ETSI/NFV has also defined 2 flavors with TOSCA and Yang.
    08:34:12 From Alexander Vul : Sure… That was the beginning of the end…
    08:34:51 From Alexander Vul : Now there are pending changes to support HEAT and K8S, and who knows what else down the line..
    08:35:34 From Alexander Vul : So if ONAP is to ever be ETSI compliant we would potentially need to support a whole bunch of encoding formats, which will require SO to bloat…
    08:36:11 From Eric Debeau : The reality is there...The cloud infra to host VNF are based on OPenStack and K8S.
    08:36:38 From Alexander Vul : Today they are, rest assured that tomorrow they won’t be
    08:37:25 From Eric Debeau : An alternative is to translate TOSCA based descriptors to HOT or Helm. To be discussed in DDF
    08:37:43 From Alexander Vul : Or the inverse… which is easier


    Zoom Attendance Log  
    Anchor
    attendees
    attendees

    TSC Members Attendance based on Zoom Chat Log: xx%89%

    AMDOCS1Alla Goldner
    AT&T1Catherine Lefevre
    Bell Canada1Alexis de Talhouët
    China Mobile1Lingli Deng
    China Telecom
    Yan Chen
    DT1Andreas Geissler
    Ericsson1Ciaran Johnston, proxy for Stephen Terrill
    Huawei1Adrian O'Sullivan, proxy for Chaker Al-Hakim
    IBM1
    Intel1Ypan Deng, proxy for Srini Addepalli 
    Nokia1Timo Perala
    Orange1Eric Debeau
    Reliance Jio1Achilles de Villa, proxy for Ning So
    Tech Mahindra1Milind Jalwadi 
    Turk Telecom
    Murat Tupcu
    Verizon1Viswa Kumar Skand Priya
    Vodafone1Davide Cherubini, proxy for Susana Sabater
    WindRiver1Bin Yang


    ...

    TSC Decisions  

    2019 TSC Decisions


    ...

    Action Items:

    •   Yipan Deng  to follow up on OPTFRA-512. Due  
    •    Yipan Deng to follow up on vCPW w/ TOSCA. Due  
    •    Benjamin Cheung  to follow up on 5G PFN pre-onboarding. Due  
    •   Scott Blandford to follow up on Scaleout / CDS at PTL meeting. Due  
    •   Seshu Kumar Mudiganti to follow up on CCVPN. Due  
    •    David Perez Caparros to follow up on BBS @ ptl meeting. Due  
    •    Bin Yang to follow up on consistent ID cloud region at PTL meeting. Due  
    •    Ciaran Johnston to follow up on SOL004. Due  
    •   Yipan Deng  to follow up on HPA sec. Due   
    •     Alexis de Talhouët FREEMAN, BRIAN D to put together a formal proposal for supercommitters at next week's TSC meeting. Due  
    •   Former user (Deleted) Rerun tool and discard readonly repos from branch list
    •   Former user (Deleted) to put forward an email  waiver vote for MUSIC
    •   cl664y@att.com will compile the information on which companies block SSH to gerrit
    •    Collect feedback about Frankfurt Activity's plan proposal from M0 to M1 (TSC-129)
    •   Adolfo Perez-Duran meet with SECCOM on a recommended version and work with PTLs
    •  El Alto M3 checklist improvements for the security questions. Paweł Pawlak
    •  (SECCOM): Review Vulnerabilities that require significant rework, architecture change as "TSC MUST Have" candidates for El Alto
    •  Brian, Jess, Paul) to create a timeline considering our ONAP release roadmap including steps required for the multi-arch pipeline

    ...