The following items are expected to be completed for the project to Pass the M4 Code Freeze Milestone.

M4 Release Code Freeze Milestone overview is available in wiki.


Info
titleUsage
  1. Use the "Copy" option (available under the ..., top right of this page) to duplicate this template into your project wiki.
  2. Fill out the Yes/No column
  3. Provide link to evidence (when necessary)


Practice AreaCheckpointYes/NoEvidencesHow to?
SecurityHas the Release Security/Vulnerability table been filled out in the   protected Security Vulnerabilities wiki space?
Table in in the protected Security Vulnerabilities wiki space   corresponds to the latest NexusIQ scan; all NexusIQ finding are marked as false positive or exploitable with the supporting analysis.
Yes/wiki/spaces/SV/pages/16089298PTL reviews the NexusIQ scans for their project repos and fills out   the vulnerability review table
Are all Defects of priority Highest and High in status "Closed" in Jira? (this includes the Jira for Critical and Severe NexusIQ findings)YesAll Jira tickets for vulnerability elimination are complete.Complete Jira tickets
Did the project achieve the enablement of transport level encryption on all interfaces and the option of disabling transport level encryption?
All interfaces are exposed over TLS  and the secure protocol can optionally be turned off
No

Progress been tacking on

Jira Legacy
serverSystem Jira
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
keyAPPC-1487

Jira Legacy
serverSystem Jira
serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
keyAPPC-1551
CDT GUI has been migrated to https - which was done after M3.

Jira Legacy
serverSystem Jira
serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
keyAPPC-1573
ODL RestConf migrate to https

Do all containers run as a non-root user and is documentation available for those containers that must run as root in order to enable ONAP features?Yes

APPC is running under odl: https://gerrit.onap.org/r/gitweb?p=ccsdk/distribution.git;a=blob;f=odlsli/odlsli-alpine/src/main/docker/Dockerfile;h=2719102e74315b9626931962fcda90c3b359cd2e;hb=4b054f9fab21f76992441e92069694d9f0cba0aa

Dgbuilder is running under dgbuilder: https://gerrit.onap.org/r/gitweb?

  • ONAP project containers do not run as the root ID with the exception of containers supporting ONAP features that require the container to run as the root ID.
  • Project containers that run as the root ID have documented this in the release notes along with the functionality that requires the container to run as the root ID.

    p=ccsdk/distribution.git;a=blob;f=dgbuilder-docker/src/main/docker/Dockerfile;h=c1fd8dbde01deefce2dcfec6b71b5987ebe9e4cb;hb=4b054f9fab21f76992441e92069694d9f0cba0aa

    CDT is running under cdt: https://gerrit.onap.org/r/gitweb?p=appc/deployment.git;a=blob;f=cdt/src/main/docker/Dockerfile;h=514ddba9d0768abeb33282926ce2a339a6177ca6;hb=d69066a2ed223fc5f525fcff520c5740736c5cb6

    Ansible is running under ansible (https://gerrit.onap.org/r/gitweb?p=ccsdk/distribution.git;a=blob;f=ansible-server/src/main/Dockerfile;h=40de69e69888c9b797dfb0e1be48cba0da9e7a74;hb=4b054f9fab21f76992441e92069694d9f0cba0aa)

     https://wiki.onap.org/display/DW/Best+Practices
    Provide the "% Achieved" on the CII Best Practices program.
    Provide link to your project CII Best Practices page.

    Passing: 98%

    Silver: 93%

    https://bestpractices.coreinfrastructure.org/en/projects/1579


    As documented in CII  Badging Program, teams have to fill out CII Best Practices
    Product ManagementHave all JIRA Stories supporting the release use case been implemented?
    By using the macro JIRA Issue/Filter, provide a link to JIRA in listing the stories that are implemented in the current Release. (Example
    Yes

    Change Management use case has been implemented/delivered for code. The rest of opened JIRAs are for testing and documentation

    Jira Legacy
    serverSystem Jira

    jqlQuerycounttrue

    project=aai and type=Story and fixversion="Amsterdam Release"

    serverId4733707d-2057-3a0f-ae5e-4fd8aff50176

    for AAI project, edit for your project)

    keyAPPC-1442

    For each JIRA story that are implemented in the current release, you have to setup in JIRA the JIRA fixVersion="Dublin Release"
    List the Stories that will not be implemented in this current Release.

    By using the macro JIRA Issue/Filter, provide a link to JIRA in listing the stories that are NOT implemented in the current release. (Example

    Jira Legacy
    serverSystem Jira
    jqlQueryproject=aai and type=Story and fixversion="Beijing Release"
    counttrue
    serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
    for AAI project, edit for your project)

    N/A


    For each JIRA story that will not be implemented in the current Release, you have to setup in JIRA the JIRA fixVersion="El Alto Release"

    Are committed Sprint Backlog Stories been coded and marked as "Closed" in Jira?
    Provide Link to Project backlog
    Yes

    Jira Legacy
    serverSystem Jira
    jqlQueryproject = "Application Controller" and affectedVersion = "Dublin Release" and status = Closed
    counttrue
    serverId4733707d-2057-3a0f-ae5e-4fd8aff50176


    Are all tasks associated with committed Sprint Backlog Stories been marked as "Closed" in Jira?Yes

    Jira Legacy
    serverSystem Jira
    jqlQueryproject = "Application Controller" and affectedVersion = "Dublin Release" and status = Closed
    counttrue
    serverId4733707d-2057-3a0f-ae5e-4fd8aff50176


    Is there any Critical and Severe level security vulnerabilities older than 60 days old in the third party libraries used within your project unaddressed?

    Nexus-IQ classifies level as the following:

    • Critical is level 7 to 10
    • Severe is level 4 to 6
    • Moderate is level 1 to 3

    which is complaint with CVSS V2.0 rating.

    In the case critical known vulnerability are still showing in the report, fill out the Security/Vulnerability Threat Template in your project.
    Yes/wiki/spaces/SV/pages/16089298Ensure the Nexus-IQ report from “Jenkins CLM” shows 0 critical security vulnerability. Open the Nexus-IQ report for the details on each repo.
    Release ManagementHave all issues pertaining to FOSS been addressed?Yes

    Have all findings from previous milestones been addressed?
    List previous milestone issues that have not been addressed.
    N/ANo FindingsFor M2 and M3 Milestones, ensure all findings have been closed.

    Has the Project Team reviewed and understood the most recent license scan reports from the LF, for both (a) licenses within the codebase and (b) licenses for third-party build time dependencies?

    Yes

    For both (a) and (b), have all high priority non-Project Licenses been either removed or escalated as likely exception requests?Yes

    DevelopmentAre all Defects of priority Highest and High in status "Closed" in Jira?YesProvide link to JIRA issue (type bug) of priority Highest and High. 
    Has the Platform Maturity Table been updated with implementation Status at M4?Yes
    For each Release, there is a Platform Maturity table created for PTLs to record their goals and achievement at M4 (Example: Casablanca Release Platform Maturity)
    Has the project team reach the Automated Unit Test Code Coverage expectation? (Refer to artifacts available in Sonar)
    Goal: 55% for Incubation project in the current release
    Yes83.8% (4/9/2019)

    Sonar

    Guidance on Code Coverage and Static Code Analysis

    Tools: Sonar
    Is there any binaries (jar, war, tar, gz, gzip, zip files) in Gerrit project repository?No
    Refer to CI Development Best Practices
    Is there any pending commit request older than 36 hours in Gerrit?NoHowever, there are some commits in Draft status - which are for R5.Gerrit Query: status:open label:verified -is:draft -label:Code-Review=-1 AND -label:Code-Review=-2  AND is:mergeable age:1week
    Are all the Jenkins jobs successfully passed (verify + merge jobs)?
    Provide link to "Merge job" as evidence in Jenkins project tab
    Yeshttps://jenkins.onap.org/view/appc/

    https://jenkins.onap.org/view/Merge-Jobs/

    Have all OOM Staging Healtcheck related to your project passed?Yes

    Are all snapshot binaries available in Nexus-staging?YesProvide link to evidence
    Do you have a clear plan to implement the Independent Versioning and Release Process by RC0?Yes
    Contact the upstream teams to make sure they will release their artifacts (in Nexus Release repo) so you can build by depending on these released artifacts by RC0.
    Integration and Testing

    Have 100% of Continuous System Integration Testing (CSIT) Use Cases been implemented successfully in Jenkins?

    It should include at least 1 CSIT that will be run on

    Lab-xxx-OOM-Daily Jenkins Job

    YesAll jobs pertaining to your project MUST pass
    Is there a Docker images available for your project deliverable?
    Provide link to Nexus repos
    Yeshttps://nexus3.onap.org/#browse/search=keyword%3DAPPC-image%20AND%20version%3D1.5.0-SNAPSHOT*

    Has the project passed the Integration Sanity Tests?

    No access for Grafana

    APPC csit is all working.

    https://jenkins.onap.org/view/appc/job/appc-master-csit-healthcheck/

    Integration sanity tests in Dublin Release cover:

    • ONAP deployment
    • All components health check
    • VNF onboarding and service creation for vFW use case
    • Model distribution for vFW
    • vFW instantiation
    • vFW closed loop
    • vFW deletion

    No test failure reported on http://onapci.org/grafana/d/8cGRqBOmz/daily-summary?orgId=1

    No Integration Blocking Issue with no workaround: Dublin Release Integration Test Blocking Issues

    Has the project code successfully passed the Daily Build process?Yeshttps://jenkins.onap.org/view/integration/ all passed that is what I am seeing.Goal is to ensure the latest project commit has not broken the Integration Daily Build

    Doc


    Does the project have a plan to finalise and close all remaining JIRA Documentation tickets?



    YesAll JIRA ticket related to Documentation will be closed and finished by RC1

    Jira Query

    project != "Sandbox Project" AND project != "ONAP TSC" AND project != CI-Management AND (labels=Documentation OR project=Documentation) AND status != Closed ORDER BY fixVersion ASC, status DESC, priority DESC, updated DESC


    Jira Query (Bugs Only)

    project != "Sandbox Project" AND project != "ONAP TSC" AND project != CI-Management AND (labels = Documentation OR project = Documentation) AND issuetype= Bug AND  fixversion = "Dublin Release" AND status != Closed ORDER BY issuetype DESC, fixVersion ASC, status DESC, priority DESC, updated DESC

    Does the project team have a plan to complete all the Release related documents by RC1?

    Yes