The following items are expected to be completed for the project to Pass the M4 Code Freeze Milestone.
M4 Release Code Freeze Milestone overview is available in wiki.
Info | ||
---|---|---|
| ||
|
Practice Area | Checkpoint | Yes/No | Evidences | How to? | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Product Management | Have all JIRA Stories supporting the release use case been implemented? | Yes |
| For each JIRA story that are implemented in Amsterdam Release, you have to setup in JIRA the JIRA fixVersion="Beijing Release" | ||||||||||
List the Stories that will not be implemented in this current Release. |
Jira Legacy | ||||||||
---|---|---|---|---|---|---|---|---|
|
No | For each JIRA story that will not be implemented in Amsterdam Release, you have to setup in JIRA the JIRA fixVersion="Beijing Release" | ||||||||||||
Are committed Sprint Backlog Stories been coded and marked as "Done" in Jira? | Yes |
| |||||||||||
Are all tasks associated with committed Sprint Backlog Stories been marked as "Done" in Jira? | Yes |
| |||||||||||
Release Management | Have all issues pertaining to FOSS been addressed? | Yes | |||||||||||
Have all findings from previous milestones been addressed? | N/A | List previous milestone issues that have not been addressed. | For M2 and M3 Milestones, ensure all findings have been closed. | ||||||||||
Has the Project Team reviewed and understood the most recent license scan reports from the LF, for both (a) licenses within the codebase and (b) licenses for third-party build time dependencies? | Yes | ||||||||||||
For both (a) and (b), have all high priority non-Project Licenses been either removed or escalated as likely exception requests? | Yes | Created a ticket#54030 to address the issues in DMaaP client project. | |||||||||||
Development | Are all Defects of priority Highest and High in status "Done" in Jira? |
Yes |
| ||||||||||||
Has the project team reach the Automated Unit Test Code Coverage expectation? (Refer to artifacts available in Sonar) | No | https://sonar.onap.org/projects?search=dmaap&sort=-analysis_date Note: - All Message router projects has 50% code coverage. - In Bus Contorller, dmaap-dbcapi and dmaap-buscontroller has met 50% code coverage. ui-dmaapbc not met the code coverage. | For evidences, provide link(s) to Gerrit repos by providing the URL as shown in this example | ||||||||||
Is there any binaries (jar, war, tar, gz, gzip, zip files) in Gerrit project repository? | No | Refer to CI Development Best Practices | |||||||||||
Is there any pending commit request older than 36 hours in Gerrit? | No | ||||||||||||
Provide the "% Achived" on the CII Best Practices program. |
97% | https://bestpractices.coreinfrastructure.org/en/projects?q=messagerouter | As documented in CII Badging Program, teams have to fill out CII Best Practices | |
Is there any Critical level security vulnerabilities older than 60 days old in the third party libraries used within your project unaddressed? Nexus-IQ classifies level as the following:
which is complaint with CVSS V2.0 rating. |
No | Some of the security vulnerabilities reported in the following checklist are less then 60 days old and some are wrongly reported. | Ensure the Nexus-IQ report from “Jenkins CLM” shows 0 critical security vulnerability. Open the Nexus-IQ report for the details on each repo. |
Are all the Jenkins jobs successfully passed (verify + merge jobs)? |
Yes | |||
Are all snapshot binaries available in Nexus? |
Yes | |||
Do you have a clear plan to implement the Independent Versioning and Release Process by RC0? | Yes | Contact the upstream teams to make sure they will release their artifacts (in Nexus Release repo) so you can build by depending on these released artifacts by RC0. | |
Integration and Testing | Have 100% of Continuous System Integration Testing (CSIT) Use Cases been implemented successfully in Jenkins? |
No | Message Router - 100%complete https://jenkins.onap.org/view/CSIT/job/dmaap-master-csit-mrpubsub/ Bus controller - In progress | |
Is there a Docker images available for your project deliverable? |
Yes | |||
Has the project code successfully passed the Daily Build process? | Yes | Goal is to ensure the latest project commit has not broken the Integration Daily Build | |
Doc | Has the team created a docs folder and Development and Release Notes documentation templates in Readthedocs? |
Yes | . | Documentation Team is using Readthedocs for documenting user facing documentation. ReadTheDcos shall be considered as a starting point for someone new within ONAP. The ReadTheDocs is the ONAP Documentation facade visible to users. | |
Is the API documentation section populated? |
No | Message router: http://onap.readthedocs.io/en/latest/submodules/dmaap/messagerouter/messageservice.git/docs/index.html Bus Controller : In progress | Ensure there is at least a direct link toward the API documentation which may be already existing in the wiki. |