Project Name | Enter the name of the project |
---|---|
Target Release Name | Beijing Release |
Project Lifecycle State | Mature Incubation (Refer to ONAP Charter, section 3.3 Project Lifecycle for further information) |
Participating Company | AT&T, Amdocs, Nokia |
Scope
What is this release trying to address?
...
VID will contribute to the following use cases:
VID will continue to support to the following use case:
Use Case: Residential Broadband vCPE (Approved)
Minimum Viable Product
- Read only "ONAP global role" permission for VID users
- Specific role assignment for components instantiations
- Change management for selected work flows (Upgrade and Configuration)
- PNF support
- Tenant Isolation for test environments
- Owning entity support
...
Sub-components are repositories and are consolidated in a single centralized place. Edit the Release Components name for your project in the centralized page.
...
Area | Actual Level | Targeted Level for current Release | How, Evidences | Comments |
---|---|---|---|---|
Performance | 0 | 1 | Do benchmark |
|
Stability | 0 | 1 | 72 hours test |
|
Resiliency | 1 | 2 | Use Galera cluster |
|
Security | 0 | 1 | Cover 50% with JUnits |
|
Scalability | 0 | 1 | Test single site horizontal |
|
Manageability | 11 | 0 |
| |
Usability | 1 | 1 | Update user guides |
|
...
List the API this project is expecting from other projects.
Prior to Release Planning review, Team Leads must agree on the date by which the API will be fully defined. The API Delivery date must not be later than the release API Freeze date.
Prior to the delivery date, it is a good practice to organize an API review with the API consumers.
...
Risk identified | Mitigation Plan | Contingency Plan |
---|---|---|
To fill out | To fill out | To fill out |
Resources
Fill out the Resources Committed to the Release centralized page.
Release Milestone
The milestones are defined at the Release Level and all the supporting project agreed to comply with these dates.
...