DRAFT PROPOSAL FOR COMMENTS
This checklist is expected to be completed for the project to pass the M1 Release Planning Milestone.
M1 Release Planning Milestone definition
Practice Area | Checkpoint | Yes/No | Evidence - Comment | How to? |
---|
Security | Has the Release Security/Vulnerability table been filled out in the protected Security Vulnerabilities wiki space? | Yes | Table in the protected Security Vulnerabilities wiki space corresponds to the latest NexusIQ scan /wiki/spaces/SV/pages/16089292 |
|
| Have known vulnerabilities (critical and severe) to address/remove in the release been identified with JIRA ticket? | Yes | Note, Shiro has new library release. This may address some Shiro Issues. | AAF-732 |
| Has the project committed to the release CII badging level? | Yes | Silver | https://bestpractices.coreinfrastructure.org/en/projects/2303 |
| Has the project created their project CII questionnaire and completed the ONAP level CII requirements | Yes | Silver | https://bestpractices.coreinfrastructure.org/en/projects/2303 |
| If the project uses java, has the project integrated with the oparent.pom? | Yes | Oparent.pom included in the project |
|
Product Management | Are Product Backlog Epics entered in Jira? | Yes | Jira Legacy |
---|
server | System Jira |
---|
jqlQuery | project= |
---|
|
|
vnfrqts holmes VNFRQTS is documentationNA | Provide a link to project Planning, Platform Maturity table. | VNFRQTS is documentationNA | VNFRQTS is documentationLink to evidence | AAF is software only | AAF deliverable are Microservices |
Has the Integration Team defined the End 2 End Release Test Case? | NA | Link to evidence |
VNFRQTS is documentation | VNFRQTS is documentation
|
Development
| Is the Project Team committed to develop Unit Test? |
NA | Yes |
| AAF has continuous improvement, and one mostly dedicated person, in addition to community help |
Has the Project Team put in place an Automated Unit Test infrastructure? |
NAVNFRQTS is documentation
| CSIT |
Is the Project Team committed to create Continuous System Integration Testing (CSIT) test case? |
NAVNFRQTS is documentation
| CSIT |
Is the Project Team committed to perform Scrum ceremonies? | Yes |
Scrum Overview
| AAF has one Team meeting per week for 1 hour. Internal Company Scrum for PTL and contractor is 15 mins a day, which includes ONAP work. |
Are the Project Team members aware of Continuous Integration Principles (don't break the build, Fix the build,...)? | Yes |
| Continuous Integration |
Has the Project Team a clear understanding on the Code Coverage expectations? |
NA VNFRQTS NA VNFRQTS AAF is documentation (in .rst) |