Table of Contents
Table of Contents
Scenario Scope In Frankfurt
This scenario will demonstrate PNF SW upgrade with netconf/yang interface with EM. The E2E procedure is VID→ SO→ CDS→ EMS → PNF. Beyond the work of scenario 1, it also need:
- Support SS REST API for PNF S/W upgrade, downloadNESw and activateNESw
Provide controller blueprint file for CDS to trigger downloadNESw and activateNESw actions
- Enhance EMS simulator for integration test
Impacts
Project/Component | Story |
---|---|
SO | Common task with Scenario 1: PNF Software Upgrade using direct Netconf/Yang interface No additional impacts |
CDS | Common task with Scenario 1: PNF Software Upgrade using direct Netconf/Yang interface Additional impact: EMS-compatiable CBA file for integration test |
Integration | 1) EMS simulator extension 2) Integration document revision for PNF Sw Upgrade UC |
JIRA Status Tracking
Jira Legacy | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|
|
Test Status
No | Test Case | Test Status |
---|---|---|
1 | Download NE SW for PNF 1 from CDS to EM using SS REST API | COMPLETE |
2 | Activate NE SW for PNF 1 from CDS to EM using SS REST API | COMPLETE |
3 | Download NE SW for PNF 2 from CDS to EM using SS REST AP | COMPLETE |
4 | Activate NE SW for PNF 2 from CDS to EM using SS REST API | COMPLETE |
5 | Test PNF SW upgrade Workflow for PNF 1 from SO to CDS to EM | NOT YET TESTED |
Detailed Description of Integration Testcases and Results
comming soon.