Release Schedule
Revision: r4 r5
Activity Log
Date | Rev | Event or Update | Milestones Affected |
---|---|---|---|
09/01/22 | r5 | The TSC pushed M3 and M4 out by one week, each to Sept 8 and Sept 22, respectively. Other milestones remain the same. Also added the Thanksgiving holiday. | M3, M4 |
07/21/22 | r4 | The TSC conditionally approved M2. | M2 |
07/14/22 | r4 | The TSC pushed M2 out one week to July 21. Also updated the sign off date shown for the Jakarta release to the actual release date (June 30). | M2 |
06/23/22 | r3 | The TSC conditionally approved M1 | M1 |
06/09/22 | r3 | The TSC approved moving M1 to June 23. | M1 |
06/02/22 | r2 | The TSC approved moving M1 to June 9 (May 24 proposal) | M1 |
05/24/22 | r2 | Updated May 19 proposal based on feedback from PTLs at May 23 PTL meeting. Moved M2 from June 30 to July 14. Still requires TSC approval. | M2 |
05/19/22 | r1 | Identified a conflict between M1 and Ascension Day on May 26, due to Ascension Day not being on the original schedule. Proposed moving M1 to June 9 and M2 to June 30. Need to review with PTLs and then vote in TSC on June 2. Added Ascension Day. | M1, M2 |
03/31/22 | initial approved | TSC approved Kohn schedule | All |
03/10/22 | First draft posted | All |
...