...
Date | Event or Update | Milestones Affected |
---|---|---|
Nov 15 | Recommended sign off to the TSC. Email vote launched. | Sign Off |
Nov 4 | The TSC delayed Sign Off to Nov 15. https://wikilf-onap.onapatlassian.orgnet/wiki/x/RZCfBgKDrs | Sign Off |
Oct 21 | The TSC approved RC under the condition that the remaining tasks will be completed by Sign Off. The TSC also approved moving the Sign Off date out one week to Nov 4 (r6). | RC, Sign Off |
Oct 18 | The TSC agreed that the requirements for RC were not reached. Will review again during the TSC meeting on Oct 21. | RC |
Oct 14 | The TSC agreed that the requirements for RC were not reached. Will review again during the PTL meeting on Oct 18, followed by an email vote. | RC |
Sept 16 | TSC approved M4 with conditions. | M4 |
Sept 9 | Remaining M3 items closed | M3 |
Sept 2 | TSC approved M3, conditioned on completion of remaining milestone tasks by M4 | M3 |
Aug 26 | TSC approved one week slip to M3. No other milestones affected (r5). | M3 |
Jun 23 | M2 approved by TSC, with exceptions, by email vote. | M2 |
May 20 | M1 approved by TSC, with exceptions. Details here. | M1 |
May 10 | Added ONESummit dates to the schedule (r4) for reference. (No changes to Istanbul release milestones from r3) | None |
May 6 | Approved by the TSC (r3) | ALL |
May 4 | New proposal (r3) in response to feedback at May 3 PTL meeting
| RC0, RC1, RC2 |
Apr 28 | New proposal (r2) in response to feedback from original proposal. | M1 - Sign Off |
Mar 18 | Proposal presentation to TSC. Requested approval of just the kickoff date of April 1. Other milestones to be discussed at a later date. TSC approved kickoff date ONLY. | M0 |
Mar 11 | Proposal presentation to TSC. TSC expressed concerns about the second half of the release occurring during the summer, which could conflict with summer holidays. Proposal not approved. | ALL |
Mar 10 | Second draft |
|
Mar 4 | Initial draft posted | N/A |
...