...
- Contract with UNH signed
- PO for servers needed to be resubmitted by Intel - delay of a few days
- HW will be delivered end of Sept / early Oct time frame
- VPN access to the servers will be configured by UNH
- Need a local jump station with access to the local BMCs
- Windriver Wind River will do OS provisioning once jump host is configured
- Bare metal will be installed with WindriverWind River's centos as is the case now
- TOR - will be using 48 port Cisco 9000s
- moves the lab from 20G throughput to 100G throughput
- Passwds will be shared between Lincoln and Stephen at least for launch -
- Windriver Wind River needs Admin access to the servers and BMCs
- Integration leads need OS admin
- Users just get user access
- No existing Intel Lab user accounts will be brought forward
- New accounts will need to be requested via https://jira.onap.org/projects/OPENLABS
- Jira will be monitored by both Windriver Wind River and UNH
- Intel lab will be decommissioned following Istanbul sign-off
- Local caching in UNH may be a future conversation from a performance standpoint
- Billing starts September beginning with rack/switch config
...