Overview

Project NameEnter the name of the project
Target Release NameIstanbul
Project Lifecycle StateIncubation
Participating Company Bell Canada, Ericsson, IBM, Highstreet, Pantheon

Scope

What is this release trying to address?

Further integrate CPS into ONAP architecture through additional components and interfaces such as

  • Network CM Proxy NCMP, moving from MVP to integrated component using SDN-C, DMaap and A&AI and an agreed new REST interface
  • ONAP Data Model Inventory (DMI) Plugin to register supported CM handles and delegate data acces to the xNFS using ODL interface in SDN-C
  • Model and Data Sync for nodes in DMI Plugin Inventory
  • Storing and querying Temporal data

Requirements

  • Jira Legacy
    serverSystem Jira
    serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
    keyREQ-717
  • Jira Legacy
    serverSystem Jira
    serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
    keyREQ-720
  • Jira Legacy
    serverSystem Jira
    serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
    keyREQ-721

Minimum Viable Product

  • Ability to add xNF (initial) inventory using 'side-door' interface
  • Read Operation support for both cached data in CPS and xNF data using 'datastores' concept
  • Write operation support for datastore ncmp-datastores:running
  • Model and Data Sync for (manually added) Simulator based xNF
  • Temporal ?

Functionalities

Epics

Jira Legacy
serverSystem Jira
serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
keyCPS-350

...

Jira Legacy
serverSystem Jira
serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
keyCPS-446

Stories


Longer term roadmap

Indicate at a high level the longer term roadmap. This is to put things into the big perspective.

Release Deliverables

Indicate the outcome (Executable, Source Code, Library, API description, Tool, Documentation, Release Note, etc) of this release.

Deliverable NameDeliverable Description
To fill outTo fill out

Sub-Components

List all sub-components part of this release.
Activities related to sub-components must be in sync with the overall release.

Sub-components are repositories and are consolidated in a single centralized place. Edit the Release Components name for your project in the centralized page.

Architecture

High level architecture diagram

At that stage within the Release, the team is expected to provide more Architecture details describing how the functional modules are interacting.

...

Anyone reading this section should have a good understanding of all the interacting modules.

Platform Maturity

Please fill out the centralized wiki page: Frankfurt Release Platform Maturity


  • API Incoming Dependencies

List the API this project is expecting from other projects.
Prior to Release Planning review, Team Leads must agreed on the date by which the API will be fully defined. The API Delivery date must not be later than the release API Freeze date.

...

API NameAPI DescriptionAPI Definition DateAPI Delivery dateAPI Definition link (i.e.swagger)
To fill outHigh level description of the APIDate for which the API is reviewed and agreedTo fill outLink toward the detailed API description
  • API Outgoing Dependencies

API this project is delivering to other projects.

API NameAPI DescriptionAPI Definition DateAPI Delivery dateAPI Definition link (i.e.swagger)
To fill outHigh level description of the APIDate for which the API is reviewed and agreedTo fill outLink toward the detailed API description
  • Third Party Products Dependencies

Third Party Products mean products that are mandatory to provide services for your components. Development of new functionality in third party product may or not be expected.
List the Third Party Products (OpenStack, ODL, RabbitMQ, ElasticSearch,Crystal Reports, ...).

...

In case there are specific dependencies  (Centos 7 vs Ubuntu 16. Etc.) list them as well.

  • Testing and Integration Plans

Provide a description of the testing activities (unit test, functional test, automation,...) that will be performed by the team within the scope of this release.

Describe the plan to integrate and test the release deliverables within the overall ONAP system.
Confirm that resources have been allocated to perform such activities.

  • Gaps

This section is used to document a limitation on a functionality or platform support. We are currently aware of this limitation and it will be delivered in a future Release.
List identified release gaps (if any), and its impact.

Gaps identifiedImpact
To fill outTo fill out
  • Known Defects and Issues

Please refer to Frankfurt Defect Status


  • Risks

List the risks identified for this release along with the plan to prevent the risk to occur (mitigation) and the plan of action in the case the risk would materialized (contingency).

Please update any risk on the centralized wiki page - Frankfurt Risks

  • Resources

Fill out the Resources Committed to the Release centralized page.

  • Release Milestone

The milestones are defined at the Release Level and all the supporting project agreed to comply with these dates.

  • Team Internal Milestone

This section is optional and may be used to document internal milestones within a project team or multiple project teams. For instance, in the case the team has made agreement with other team to deliver some artifacts on a certain date that are not in the release milestone, it is erecommended to provide these agreements and dates in this section.

...

DateProjectDeliverable
To fill outTo fill outTo fill out
  • Documentation, Training

Please update the following centralized wiki: Frankfurt Documentation

...

Note
titleNote

The Documentation project will provide the Documentation Tool Chain to edit, configure, store and publish all Documentation asset.


Other Information

  • Vendor Neutral

If this project is coming from an existing proprietary codebase, ensure that all proprietary trademarks, logos, product names, etc. have been removed. All ONAP deliverables must comply with this rule and be agnostic of any proprietary symbols.

  • Free and Open Source Software

FOSS activities are critical to the delivery of the whole ONAP initiative. The information may not be fully available at Release Planning, however to avoid late refactoring, it is critical to accomplish this task as early as possible.
List all third party Free and Open Source Software used within the release and provide License type (BSD, MIT, Apache, GNU GPL,... ).
In the case non Apache License are found inform immediately the TSC and the Release Manager and document your reasoning on why you believe we can use a non Apache version 2 license.

...