Name | |
Milestone or Requirements Exception? | Milestone |
Project or Requirement Name and JIRA | Usecase UI
|
Milestones affected | RC0
|
Projects affected | Usecase UI |
Background description | Since Usecase UI had request to be merged after M3, we submitted the request to OOM. But OOM thought it was too late after M3, so we decided to postpone the merge date of UUI NLP which was a new module of UUI and still had several problems. So we abandoned the commit request of UUI NLP and asked the OOM team wether the rest part of UUI module could be merged into H release |
Schedule impact | N/A
|
Recovery plan | We abandoned the UUI NLP module and requested for merging again |
Milestone schedule change | If not approved, the release plan of UUI module will postpone to next release |
Risk | N/A |
Status | ClosedApproved |
Decision | Approved: See- https://wiki.onap.org/x/sgPxBQ |