What is this release trying to address?

Describe the problem being solved by this releaseGeneral project tasks:

Support in producing documentation for ONAP releases

Define guidelines and tooling for documentation handling across all ONAP projects

Release specifics:

Improve templates

Refine the documentation guide

Requirements

Describe the use case this release is targeted for (better if reference to customer requirements).

Minimum Viable Product

Describe the MVP for this release.

Functionalities

List the functionalities that this release is committing to deliver by providing a link to JIRA Epics and Stories. In the JIRA Priority field, specify the priority (either High, Medium, Low). The priority will be used in case de-scoping is required. Don't assign High priority to all functionalities.

...

Jira Legacy
serverSystem Jira
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
maximumIssues20
jqlQueryproject=sanbox doc and issuetype in (epic)
serverId4733707d-2057-3a0f-ae5e-4fd8aff50176

...

Jira Legacy
serverSystem Jira
columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
maximumIssues20
jqlQueryproject=sanbox doc and issuetype in (story)
serverId4733707d-2057-3a0f-ae5e-4fd8aff50176

...

Deliverable NameDeliverable Description
To fill outTo fill outRelease documentation Ensure that the project delivers documentation according to expectations

Sub-Components

List all sub-components part of this release.
Activities related to sub-components must be in sync with the overall release.

Sub-components are repositories and are consolidated in a single centralized place. Edit the Release Components name for your project in the centralized page.

Architecture

High level architecture diagram

...

List the API this project is expecting from other projects.
Prior to Release Planning review, Team Leads must agreed on the date by which the API will be fully defined. The API Delivery date must not be later than the release API Freeze date.

Prior to the delivery date, it is a good practice to organize an API review with the API consumers.

...

API NameAPI DescriptionAPI Definition DateAPI Delivery dateAPI Definition link (i.e.swagger)
To fill outHigh level description of the APIDate for which the API is reviewed and agreedTo fill outLink toward the detailed API description
  • Third Party Products Dependencies

Third Party Products mean products that are mandatory to provide services for your components. Development of new functionality in third party product may or not be expected.
List the Third Party Products (OpenStack, ODL, RabbitMQ, ElasticSearch,Crystal Reports, ...).

...

In case there are specific dependencies  (Centos 7 vs Ubuntu 16. Etc.) list them as well.

  • Testing and Integration Plans

...

description

...

  • Gaps

This section is used to document a limitation on a functionality or platform support. We are currently aware of this limitation and it will be delivered in a future Release.
List identified release gaps (if any), and its impact.

...


  • Known Defects and Issues

Please refer to Frankfurt Defect Status

  • Risks

List the risks identified for this release along with the plan to prevent the risk to occur (mitigation) and the plan of action in the case the risk would materialized (contingency).

Please update any risk on the centralized wiki page - Frankfurt Risks

  • Resources

Fill out the Resources Committed to the Release centralized page.

  • Release Milestone

The milestones are defined at the Release Level and all the supporting project agreed to comply with these dates.

  • Team Internal Milestone

This section is optional and may be used to document internal milestones within a project team or multiple project teams. For instance, in the case the team has made agreement with other team to deliver some artifacts on a certain date that are not in the release milestone, it is erecommended to provide these agreements and dates in this section.It is not expected to have a detailed project plan.

...

  • Documentation, Training

Please update the following centralized wiki: Frankfurt Documentation

...