Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

MilestoneDate Deliverable

Notes

Dev1 Start

 

Vetted Jira list for the EarlyDrop (ED)List of planned jiras for the development sprint (M1)
M1 checkpoint

 

TSC reviews and sign-off on intended El Alto Content

Content defined by fixVersion = "El Alto Release"

Early Drop content defined by: label contains "El_Alto_Early_Drop"

Test Plan Review

 

Early drop and Final release test plan review and sign off by TSC


Test1 Start

 

Test to deliver ED

Phased integration and test plan. (M4_early_drop)

Run daily sanity on El Alto released images, and start vFW, vLB and vCPE use case testing

Dev1 End

 

Priority 0 vulnerabilities addressed

List of completed jiras due

API documentation complete

Arch changes reviewed and documented

Dev2 Start

 

Fixes only to support ED

Integration team drives bug list priority. All other development deferred check in until Dev3

Integration will work with dev teams to close highest/high priority jiras discovered during 

integration test. All integration tests should be finished three days before ED release so we 

will have time to update release note, put tag on branches, etc.

Dev2 End

 

ED released Complete release - includes rel_notes, named release, branch.
Test1 End

 

ED releasedComplete release - includes rel_notes, named release, branch.
EarlyDrop

 



Dev3 Start

 



Test2 Start

 



Dev3 End

 


(M4)
Test2 End

 



Test3 Start

 


Pair-wise testing (1 wk only)  and Integration (RC0)
Test3 End 

 



El Alto Release

 



...