Milestone | Date | Deliverable | Notes |
---|---|---|---|
Dev1 Start |
| Vetted Jira list for the EarlyDrop (ED) | List of planned jiras for the development sprint (M1) |
M1 checkpoint |
| TSC reviews and sign-off on intended El Alto Content | Content defined by fixVersion = "El Alto Release" Early Drop content defined by: label contains "El_Alto_Early_Drop" |
Test Plan Review |
| Early drop and Final release test plan review and sign off by TSC | |
Test1 Start |
| Test to deliver ED | Phased integration and test plan. (M4_early_drop) |
Dev1 End |
| Priority 0 vulnerabilities addressed | List of completed jiras due API documentation complete Arch changes reviewed and documented |
Dev2 Start |
| Fixes only to support ED | Integration team drives bug list priority. All other development deferred check in until Dev3 |
Dev2 End |
| ED released | Complete release - includes rel_notes, named release, branch. |
Test1 End |
| ED released | Complete release - includes rel_notes, named release, branch. |
EarlyDrop |
| ||
Dev3 Start |
| ||
Test2 Start |
| ||
Dev3 End |
| (M4) | |
Test2 End |
| ||
Test3 Start |
| Pair-wise testing (1 wk only) and Integration (RC0) | |
Test3 End |
| ||
El Alto Release |
|
...