# | Objective | How Achieved | Participant Preparation required | Action items out |
---|---|---|---|---|
3 | Review JIRA Backlog. Participants should be comfortable that they understand the backlog of tasks for our project ( 5 min) Close Sprint 20 | Walk through the JIRA backlog to check for completeness | review: docs.onap.org ( latest) vnf guidelines open gerritt vnf requirments open gerritt vnf test open gerrit vnf use cases open gerritt | |
4 | Develop Next Sprint Participants should be comfortable with an achievable development sprint scope ( 30 min) Start Sprint 21 | Walk through the JIRA backlog | ||
5 | Relationships with other projects (10 min) | review project handoffs | review handoffs with others? | create any necessary User Stories |
6 | Release Planning: Dublin: RC0: May 2, 2019 RC1: May 09, 2019 RC2: May 23, 2019 Signoff: May 30, 2019 El Alto Frankfurt | Candidate VNFRQTS work items for Dublin | update Project Release Plan & Release EPICs |
7. Any other Business? (5 min)
Test case Description / framework for testing live VNF instances:
- third party test labs must be able to run test cases and generate reports for VNF certification
- operators must be able to run test cases against VNFs that have been onboarded.
- needs to be decided and documented before end of El Alto
- blocks VNF test case development