2019-05-22 VNFRQTS Weekly Project meeting WEDNESDAY
Agenda:
Antitrust Policy Statement: Meetings of the ONAP Project involve participation by industry competitors, and it is the intention of the Project to conduct all of its activities in accordance with applicable antitrust and competition laws. It is therefore extremely important that attendees adhere to meeting agendas, and be aware of and not participate in any activities that are prohibited under applicable U.S. state, federal or foreign antitrust and competition laws. Examples of types of actions that are prohibited at ONAP Project meetings and in connection with ONAP Project activities are described in the The Linux Foundation Antitrust Policy. If you have questions about these matters, please contact your company counsel or Andrew Updegrove, of the firm of Gesmer Updegrove LLP, which provides legal counsel to The Linux Foundation. Linux Foundation Antitrust Policy: https://www.linuxfoundation.org/antitrust-policy
Assemble/Welcome (5 min)
# | Objective | How Achieved | Participant Preparation required | Action items out |
---|---|---|---|---|
3 | Review JIRA Backlog. Participants should be comfortable that they understand the backlog of tasks for our project ( 5 min) Close Sprint 20 | Walk through the JIRA backlog to check for completeness | review: docs.onap.org ( latest) vnf guidelines open gerritt vnf requirments open gerritt vnf test open gerrit vnf use cases open gerritt | |
4 | Develop Next Sprint Participants should be comfortable with an achievable development sprint scope ( 30 min) Start Sprint 21 | Walk through the JIRA backlog | ||
5 | Relationships with other projects (10 min) | review project handoffs | review handoffs with others? | create any necessary User Stories |
6 | Release Planning: Dublin: RC2: May 23, 2019 Signoff: May 30, 2019 El Alto Frankfurt |
Candidate VNFRQTS work items for Dublin |
| update Project Release Plan & Release EPICs |
7. Any other Business? (5 min)
Test case Description / framework for testing live VNF instances:
third party test labs must be able to run test cases and generate reports for VNF certification
operators must be able to run test cases against VNFs that have been onboarded.
needs to be decided and documented before end of El Alto
blocks VNF test case development
Meeting Notes