Info | ||
---|---|---|
| ||
|
Practice Area | Checkpoint | Yes/No | Evidences | How to? |
---|---|---|---|---|
Product Management | Are all tasks associated with the release been marked as "Closed" in Jira? | Link to Jira | ||
Have all findings from previous milestones been addressed? | Provide link to JIRA findings | |||
Development | Have all Defects of priority Highest and High been in status "Closed" in Jira? | Provide link to JIRA issue (type bug) of priority Highest and High. | ||
Are all JIRA issues used as a reference in a commit in status "Closed" in Jira? | Very often, some JIRA issue remains in status "Todo" in JIRA while the commit they are referenced to is successful. | |||
Is there any pending commit related to Highest and High priority issues older than 36 hours in Gerrit? In case there are messages going back and forth between authors and reviewers, it is acceptable to be above 36 hours. | Gerrit Query: status:open label:verified -is:draft -label:Code-Review=-1 AND -label:Code-Review=-2 AND is:mergeable age:1week | |||
Are all the Jenkins jobs successfully passed (verify + merge jobs)? | Provide link to "Merge job" as evidence in Jenkins project tab | https://jenkins.onap.org/view/Merge-Jobs/ | ||
Has the project team reach the Automated Unit Test Code Coverage expectation? (Refer to artifacts available in Sonar) | Goal: 55% for Incubation project in the current release | Guidance on Code Coverage and Static Code Analysis Tools: Sonar | ||
Has the team delivered all their release artifacts in Nexus Release repo? There should be at least ONE version of each artifacts available in Nexus Release repo. | Refer to Independent Versioning and Release Process for procedure | |||
Integration and Testing | Have all CSIT Use Cases (created by each project team) passed? It should include at least 1 CSIT that will be run on Lab-xxx-OOM-Daily Jenkins Job | Provide link to evidence. As things are moving fast, we want to ensure CSIT are still "green". | ||
At RC0, has the Pair Wise testing table been filled out? | Casablanca Pair Wise Testing master page | |||
At RC0, have all OOM Release Healtcheck related to your project passed? | ||||
At RC0, is there a Docker image in Nexus Docker-Release repo available for each repository? | Provide link to evidence | |||
Has the project code successfully passed the Daily Build process? | Goal is to ensure the latest project commit has not broken the Integration Daily Build | |||
Has the OOM deployment passed? | Ensure in Jenkins External Labs all Health Check pass. | |||
Has the |
(not a gating item for Casablanca)
Ensure in Jenkins External Labs all Health Check pass.project passed the Integration Sanity Tests? | Integration sanity tests in Dublin Release cover:
No test failure reported on http://onapci.org/grafana/d/8cGRqBOmz/daily-summary?orgId=1 No Integration Blocking Issue with no workaround: Dublin Release Integration Test Blocking Issues | |||
Documentation | For RC0, for project delivering binaries, has the team populated and validated all the sections of either the Platform Component or SDK template? | Most teams have already created the high level file structures in readthedocs, and populated some actual documentation. However, the remaining sections of the appropriate teamplate must be completed. Platform: A&AI, APP-C, CLAMP, CLI, DCAE, DMaaP, Holmes, MSB, OOM, Policy, Portal, SDN-C SDC, SO, UseCase UI, VFC, VID SDKs: AAF, CCSDK, External API Framework, Multi VIM/Cloud, VNFSDK | ||
For RC1, has the team addressed any issue (recorded in JIRA) provided by the Documentation team? | ||||
For RC2, for project delivering binaries, has the team populated and validated all the sections of the Release Notestemplate? | ||||
For RC2, has the Documentation Team provided the final approval for your project documentation? |