Review | Milestone | Date | Events |
---|---|---|---|
Last day for Service Providers to submit their priorities for Dublin | Nov 1, 2018 | ||
Last day for overall providing use case/functional requirements as a candidates for Dublin | Nov 15, 2018 | ||
Kick-Off (Open Intent To Participate) | M0 | Nov 15, 2018 | Opening of Release Planning
|
Last day for getting all of the requirements (architecture, security, projects, S3P etc.) and getting a single consolidated list so all of the projects have full picture of what is required from them. | Nov 29, 2018 | By this date, all use cases/functional requirements need to be discussed with a different projects, and demanded scope of development should be clear to the projects: For use cases/functional requirements:
(link to current use cases/functional requirements proposals description: | |
Project Submission Closure | Nov 30, 2018 | Last Date to announce Intention to Participate | |
Project Proposal Approved | Dec 13, 2018 | The TSC has a goal to review and provide its disposition on all submitted projects proposal. This is the last date for TSC to formally approved New Project Proposal | |
Project Planning Closure | Jan 10, 2019 | Project Planning submission, by this date all projects have submitted in wiki their Release Planning materials. That will give everyone to time to understand project scope and dependencies. | |
Planning | M1 | Jan 17, 2019 | Planning process complete, all Project Deliverables are defined (including functional architecture, scope, dependencies,...) Integration Team has defined the vendor Equipments list and the End 2 End Release Test Cases are fully defined. The Document and Training teams have defined their plans. The packaging and installation strategy is defined. To pass the M1 milestones, all approved projects have to:
|
Functionality freeze | M2 | Feb 14, 2019 | Functionality freeze, no new visible functionality is to be added to the current ONAP release. Each Project team has defined and documented their Functional Test Cases. The vendor equipments have been delivered. A stable document describing the API is documented and available in wiki. |
API Freeze | M3 | March 07, 2019 | API/data model freeze. Mark the end of API and Data Model change. API and Data Model are now Frozen. Any changes to the API must be brought to the knowledge of the TSC for review and approval. 50% of Functional Test Case are automated. |
Code Freeze | M4 | March 28, 2019 | Code Freeze. Mark the end of the Features coding. Jira issues are either fixed in the current release or assigned to next release. 100% of Functional Test Case are automated. End 2 End Release Test Cases are implemented (Integration Team). |
Integration | RC0 | April 18, 2019 | Release Candidate 0 RCs are to ensure proper alignment and execution on End 2 End Release Test Cases and End 2 End functional Test Cases. Project Team focused its effort on:
|
RC1 | May 02, 2019 | Release Candidate 1 | |
Marketing: Outline for written content agreed with LF marketing | May 09, 2019 | ||
Marketing: Near-final draft for written content | May 16, 2019 | ||
RC2 | May 16, 2019 | Release Candidate 2 | |
Marketing: Content freeze | May 23, 2019 | ||
Marketing: New video content | May 23, 2019 | ||
Sign-Off | Release Delivery | May 23, 2019 | Dublin Release Sign-Off |
Marketing: Public announcement | May 30, 2019 TBD |
...