This page summarizes the projects participating into Casablanca Release.
...
July 19 Update: Scope Change. From a Casablanca scope perspective, there are 2 additional functional requirements added:
- Change Management – Trafic Migration
- Change Management – PNF Software Upgrade
Slide deck has been updated accordingly. View file name ONAP Casablanca M1 Status Summary Version5.pdf height 250
M2 Status
All projects passed M2 Functionality Freeze. TSC Approval (Topic #5, Section Y )
View file name ONAP Casablanca M2 Status Summary Version1.pdf page TSC 2018-07-26 height 250
View file name ONAP Casablanca Release Checklist V2.pdf page TSC 2018-07-26 height 250
M3 Status
M3 review took place on August 23, 2018.
...
- Slide #4: Michael Lando to review Bugs impacting HPA
1 SDC defect fixed, one still in WIP. ETA: planned for beg next week.Status colour Green title Done - Slide 7-12: Vimal Begwani to provide status on 5 G implementation STATUS
Status colour Yellow title WIP
5G Plug & Play: Brian Freeman Follow up on PRH HealthCheck within DCAEStatus colour Green title Done
5G/PNF: Lifecycle Managament Support: Tracy Van Brakle and Jorge Hernandez to confirm that the necessary Ansible playbooks were delivered,
and the necessary directed graph updates were made to invoke those playbooks
5G: Bulk PM: Vimal Begwani File collector WIP. ETA Oct 4.Status colour Green title Done - Slide 12: Sarat Puthenpura to provide ETA on 5G Performance Analysis and Optimization STATUS
Status colour Green title Done - Slide #16: PTLs to update Casablanca Platform Maturity table at https://wiki.onap.org/display/DW/Casablanca+Release+Platform+Maturity.
Modeling (Hui Deng), VID (Ofir Sonsino)Status colour Red title Missing - Slide #16: Gildas to add Platform Maturity table in M4 checklist. STATUS
Status colour Green title Done - Slide #23: cl664y@att.com to update status on OSAM/PNF (postpone to Dublin or not) STATUS:
OSAM postpone to Dublin.Status colour Yellow title Postponed - Slide #25: Impacted PTLs to fix CSIT Failure. STATUS
for DCAE, Multicloud, VFC, ExtAPI, DMAAP,OOF.Status colour Green title Done - Slide #27: Jonathan Gathman and Michael Lando to increase code coverage for aaf-auth and sdc master and provide update on repos for which there is no report in Sonar.
...
- Slide #28: Impacted PTLs to publish Vulnerability report. Steven Wright to follow up with Gildas Lanilis Gmail for VVP. STATUS
for VVP, Multicloud, Modeling, MUSICStatus colour Green title Done
UseCase UI (Tao Shen)Status colour Red title Missing - Slide #29-30: Impacted PTLs: Clean or Fix Job Failure
Logging(Michael O'Brien)Status colour Red title FAILURE
for APPC,HOLMES, AAI, AAFStatus colour Green title Done - Slide #32: OOF team to ensure Healthcheck passes. STATUS
OOF pass on both Wind River OOM Release and Staging.Status colour Green title Done - Slide # 33 Risks: Jonathan Gathman and Manoop Talasila to address risks #3 on CADI. STATUS: Risk #3 closed.
Status colour Green title Done
...
- APPC
- CCSDK
- DCAE
- Log
- Multivim
- Music
- Portal
- SDC
- Usecase UI
RC2 Status
By TSC decision on Nov 8, RC2 Milestone has been pushed to Tuesday, Nov 27 and Release Sign-Off to Friday, Nov 30.
Casablanca Milestones Status
...