This template must be filled out for every Release Candidate Milestone (RC0, 1, 2, x)

RC Release Candidate Milestone overview is available in wiki.


Info
titleUsage
  1. Use the "Copy" and "Move" options (available under the ..., top right of this page) to duplicate this template into your project wiki.
  2. Fill out the Yes/No column
  3. Provide link to evidence (when necessary)
Practice AreaCheckpointYes/NoEvidencesHow to?
Product ManagementAre all tasks associated with the release been marked as "Closed" in Jira?Yes


Have all findings from previous milestones been addressed?

Dynamic cloud owner SO-1128

SO <->SDNC interface over the cloud

region

configuration



DevelopmentHave all Defects of priority Highest and High been in status "Closed" in Jira?


Are all JIRA issues used as a reference in a commit in status "Closed" in Jira?Yes
Very often, some JIRA issue remains in status "Todo" in JIRA while the commit they are referenced to is successful.
Is there any pending commit related to Highest and High priority issues older than 36 hours in Gerrit? In case there are messages going back and forth between authors and reviewers, it is acceptable to be above 36 hours.No

Are all the Jenkins jobs successfully passed (verify + merge jobs)?Yeshttps://jenkins.onap.org/view/so/

Has the team delivered all their release artifacts in Nexus Release repo?

There should be at least ONE version of each artifacts available in Nexus Release repo.

Yes

https://nexus.onap.org/content/repositories/staging/org/onap/so/

https://nexus.onap.org/content/repositories/releases/org/onap/so/

Refer to Independent Versioning and Release Process for procedure
Integration and TestingHave all CSIT Use Cases (created by each project team) passed?Yeshttps://jenkins.onap.org/view/CSIT/
At RC0, has the Pair Wise testing table been filled out?WIP

Casablanca Pair Wise Testing master page



At RC0, have all OOM Release Healtcheck related to your project passed?Yes

At RC0, is there a Docker image in Nexus Docker-Release repo available for each repository?Yeshttps://nexus3.onap.org/#browse/browse:docker.snapshot
Has the project code successfully passed the Daily Build process?Yes
Goal is to ensure the latest project commit has not broken the Integration Daily Build 
Has the OOM deployment passed?YesEnsure in Jenkins External Labs all Health Check pass. since 24th

Has the Heat deployment passed?

(not a gating item for Casablanca)

NAEnsure in Jenkins External Labs all Health Check pass.
Documentation

For RC0, for project delivering binaries, has the team populated and validated all the sections of either the Platform Component or SDK template?


Yes

See https://onap.readthedocs.io/en/latest/submodules/vnfsdk/model.git/docs/index.html


Note that VNFSDK fits neither the Platform nor the SDK templates. We have filled out the relevant sections.

Most teams have already created the high level file structures in readthedocs, and populated some actual documentation. However, the remaining sections of the appropriate template must be completed.

Platform: A&AI, APP-C, CLAMP, CLI, DCAE, DMaaP, Holmes, MSB, OOM, Policy, Portal, SDN-C SDC, SO, UseCase UI, VFC, VID

SDKs: AAF, CCSDK, External API Framework, Multi VIM/Cloud, VNFSDK

For RC1, has the team addressed any issue (recorded in JIRA) provided by the Documentation team?

N/ANo JIRA tickets from Documentation team



For RC2, for project delivering binaries, has the team populated and validated all the sections of the Release Notestemplate?

NA

For RC2, has the Documentation Team provided the final approval for your project documentation?NA