Review | Milestone | Date | Events |
---|---|---|---|
Kick-Off (Open Intent To Participate) | M0 | November 16, 2017 | Opening of Release Planning
|
Project Submission Closure | November 30, 2017 | Last Date to announce Intention to Participate | |
Project Proposal Approved | December 13, 2017 | The TSC has a goal to review and provide its disposition on all submitted projects proposal. This is the last date for TSC to formally approved New Project Proposal | |
Project Planning Closure | Jan 8, 2017 | Project Planning submission, by this date all projects have submitted in wiki their Release Planning materials. That will give everyone to time to understand project scope and dependencies. | |
Planning | M1 | Jan 18, 2018 | Planning process complete, all Project Deliverables are defined (including functional architecture, scope, dependencies,...) Integration Team has defined the vendor Equipments list and the End 2 End Release Test Cases are fully defined. The Document and Training teams have defined their plans. The packaging and installation strategy is defined. To pass the M1 milestones, all approved projects have to:
|
Functionality freeze | M2 | Feb 12, 2018 | Functionality freeze, no new visible functionality is to be added to the current ONAP release. Each Project team has defined and documented their Functional Test Cases. The vendor equipments have been delivered. A stable document describing the API is documented and available in wiki. |
API Freeze | M3 | March 8, 2018 | API/data model freeze. Mark the end of API and Data Model change. API and Data Model are now Frozen. Any changes to the API must be brought to the knowledge of the TSC for review and approval. 50% of Functional Test Case are automated. |
Code Freeze | M4 | March 29, 2018 | Code Freeze. Mark the end of the Features coding. Jira issues are either fixed in the current release or assigned to next release. 100% of Functional Test Case are automated. End 2 End Release Test Cases are implemented (Integration Team). |
Integration | RC0 | Avril 19, 2018 | Release Candidate 0 RCs are to ensure proper alignment and execution on End 2 End Release Test Cases and End 2 End functional Test Cases. Project Team focused its effort on:
|
RC1 | May 3, 2018 | Release Candidate 1 | |
RC2 |
May 31, 2018 | Release Candidate 2 TSC decision to postpone RC2 review by 2 weeks (Topic 3, section am) | |
Sign-Off | Release Delivery |
June 7, 2018 | Beijing Release Sign-Off TSC decision to postpone RC2 review by 2 weeks (Topic 3, section am) |
...