- OOM Casablanca - M4 Deliverable for Code Freeze Milestone Checklist passed on Thursday September 20
- there are still "core" stories that are in progress and have not been marked closed - OOM Casablanca - M3 Architecture Review
- please update status of all JIRA issues assigned to you to reflect accurate state
- the closing of some stories were dependent on creation of new documentation stories for Casablanca or new stories for Dublin - not sure this has been done yet
- please help to clear out overdue reviews: https://gerrit.onap.org/r/#/q/project:oom+and+status:open+and+age:%253E36h+-status:draft
- there are still "core" stories that are in progress and have not been marked closed - OOM Casablanca - M3 Architecture Review
- Review work in progress for current sprint: Casablanca-M4 (09/20)