Review MilestoneDateEvents
Kick-Off (Open Intent To Participate)M0May 25, 2018

Opening of Release Planning

Project Submission Closure
June 07, 2018

Last Date to announce Intention to Participate

Project Proposal Approved
June 14, 2018The TSC has a goal to review and provide its disposition on all submitted projects proposal.

This is the last date for TSC to formally approved New Project Proposal

Project Planning Closure
June 21, 2018

Project Planning submission, by this date all projects have submitted in wiki their Release Planning materials.

That will give everyone to time to understand project scope and dependencies.

PlanningM1June 28, 2018

Planning process complete, all Project Deliverables are defined (including functional architecture, scope, dependencies,...)

Integration Team has defined the vendor Equipments list and the End 2 End Release Test Cases are fully defined.

The Document and Training teams have defined their plans. The packaging and installation strategy is defined.

To pass the M1 milestones, all approved projects have to:

  1. Fill out the Release Planning Template
  2. Fill out the Deliverables for Planning Milestone Checklist Template
  3. Post these 2 project deliverables in wiki.
Functionality freezeM2July 26, 2018

Functionality freeze, no new visible functionality is to be added to the current ONAP release.

Each Project team has defined and documented their Functional Test Cases.

The vendor equipments have been delivered.

A stable document describing the API is documented and available in wiki.

API FreezeM3August 23, 2018

API/data model freeze. Mark the end of API and Data Model change. API and Data Model are now Frozen.

Any changes to the API must be brought to the knowledge of the TSC for review and approval.

50% of Functional Test Case are automated.

Code FreezeM4Sept 20, 2018

Code Freeze. Mark the end of the Features coding.

Jira issues are either fixed in the current release or assigned to next release.

100% of Functional Test Case are automated.

End 2 End Release Test Cases are implemented (Integration Team).

IntegrationRC0Oct 11, 2018

Release Candidate 0

RCs are to ensure proper alignment and execution on End 2 End Release Test Cases and End 2 End functional Test Cases.

Project Team focused its effort on:

  1. supporting integration testing
  2. closing high priority defects
  3. supporting Documentation team

RC1Oct 25, 2018Release Candidate 1
Marketing: Outline for written content agreed with LF marketing 
Nov 1, 2018
Marketing: Near-final draft for written content 
Nov 8, 2018

RC2Nov 08, 2018Release Candidate 2
Marketing: Content freeze 
Nov 15, 2018
Marketing: New video content
Nov 15, 2018
Sign-OffRelease DeliveryNov 15, 2018Casablanca Release Sign-Off
Marketing: Public announcement 
Nov 29, 2018


Beijing Release

This release calendar below has been approved by TSC at Santa Clara Developers F2F  on Dec 13, 2017.

...