- All design cases confirm that they are on track to meet M4 (vCPE Design and Test Cases)
- Service model revised to simplify SO workflow designs. Robot will be used extensively to orchestrate decomposed services in vCPE.
- Dan Timony confirmed that he will work on the required Yang and DGs for SDNC.
VoLTE
- SDNC team worked with equipment vendors of overlay network and jointly defined overlay TOSCA template. Underlay network development is on track.
- Talked with Policy team to make sure all the development work to support VoLTE is on track.
- A&AI team suggested VFC team to reuse existing node type instead of creating new one.
Developer Lab
- Installed and tested ONAP1.1 last week and 6 VMs failed sanity test. Created JIRA tickets for all the blocking issues for sanity test. With the latest update,
4 VMs(DCAE, SDNC, APPC and MSO) are still failing sanity test
- Worked with integration team to scrub JIRA high priority bug reports, and selected top blocking issues Integration Test Blocking Issues
E2E Integration Lab
- The ONAP deployment environment is ready. Deployed WindRiver Titanium R4, the same with Developer lab.
- ZTE and Huawei's tasks in TIC core are done
- Huawei and ZTE, are deploying VNFs in TIC Edge to integrate with VIO 4.0, still in process.
- Nokia is deploying vISCSCF, more virtual resources will be added to TIC core will extend more compute nodes.