Sub-components are repositories are consolidate in a single centralized place. Edit the Release Components name for your project in the centralized page.
...
Risk identified | Mitigation Plan | Contingency Plan |
---|---|---|
code to be scrubbed for release to ONAP | additional resources assigned | include in Beijing release |
Resources
Fill out the Resources Committed to the Release centralized page.
Release Milestone
The milestones are defined at the Release Level and all the supporting project agreed to comply with these dates.
...
Date | Project | Deliverable |
---|---|---|
5/4/17 | M0 | Kickoff |
6/29/17 | M1 | Planning process Complete |
8/3/17 | M2 | Functionality Freeze |
8/24/17 | M3 | API/Data Model Freeze |
8/31/17 | SPRINT Sprint 1 | sprint-1 created |
9/14/17 | M4 SPRINT Sprint 2 | Code Freeze Sprint 1 complete, Sprint 2 created |
9/28/17 | RC0 SPRINT Sprint 3 | Release Candidate 0 Sprint 2 complete, Sprint 3 created |
10/12/17 | RC1 Sprint 4 | Release Candidiate 1 Sprint 3 complete, Sprint 4 created |
10/26/17 | RC2 Sprint 5 | Release Candidiate 2 Sprint 4 complete, Sprint 5 created |
11/2/17 | Release Delivery | Target Release Date |
...
Each project must edit its project table available at FOSS VNF SDK.
Charter Compliance
The project team comply with the ONAP Charter.