ReviewMilestoneDescriptionActivities

Kick-Off

(Open Intent to Participate)

M0
  • The goal of the Kick-Off review is to declare intention to participate in an ONAP Release.
  • The proposed Project aligns with the architecture, team is in place, draft project plan is well-formed in wiki. 
  • Once approved, the planning process opens.
  • Once approved, the team can start refining architecture, coding, testing, and documenting.
  • Release Kick-Off review takes place for each next releases.
  • TSC formally provides its formal disposition.
To reach Release Kick-Off review, the team must:

Once the Release Kick-Off passed, the following activities are performed:

  • Release Use Case are iteratively worked on, submitted to TSC and proposed to GB.
  • Development of feature code.
  • Development of feature test case.
  • Continuous Integration Continuous Delivery process is created (All repositories are created).
  • The Integration Team defines an End to End Release Test Case.

...