We will start our meetings by mentioning the project's Antitrust Policy, which you can find linked from the LF and project websites. The policy is important where multiple companies, including potential industry competitors, are participating in meetings. Please review and if you have any questions, please contact your company legal counsel. Members of the LF may contact Andrew Updegrove at the firm Gesmer Updegrove LLP, which provides legal counsel to the LF.

Table of Contents
maxLevel1

...

Attendance is taken purely upon #info in Zoom Chat 


Time
(mins)

Agenda Items

Presented By

Presos/Notes/Links/

45

Release Status

  • Guilin RC1
    • Schedule
      • Propose combining RC1 with RC2 / Sign Off on Nov 19.
      • #AGREED The TSC approves Rc1, Rc2 and Sing-Off as all occurring on Nov. 19th
    • Ongoing issues with OOM/SO
      • Jira Legacy
        showSummaryfalse
        serverSystem Jira
        columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
        serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
        keySO-3322
      • Jira Legacy
        showSummaryfalse
        serverSystem Jira
        columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
        serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
        keySO-3346
      • Jira Legacy
        showSummaryfalse
        serverSystem Jira
        columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
        serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
        keySO-3352
    • Java Upgrade issue
      • Jira Legacy
        showSummaryfalse
        serverSystem Jira
        columnskey,summary,type,created,updated,due,assignee,reporter,priority,status,resolution
        serverId4733707d-2057-3a0f-ae5e-4fd8aff50176
        keyAAI-3219
         (Zu Qiang )
    • Guilin Milestone Status 
    • Issue status (i.e., non-relman)
    • Integration status
  • Guilin RC2


  • Honolulu
    • Schedule proposed
      • Please review and send feedback to David McBride .  Be prepared to vote on the schedule on Nov 19. 
      • PTLs: Please complete survey regarding PTL availability in December.
      • Note: Krzysztof Opasiak says that release requirements may be approved when ready any time between M0 and M2.
    • TSC Initial Feedback on Requirements
      • Honolulu Release Requirements - 3 Use cases; 13 functional requirements (2 submitted post deadline) and 12 non functional requirements (1 submitted post-deadline)
      • M1 approval field was used to provide some feedback - only 4 functional requirements are candidate to be approved
      • Any new requirement submitted after Oct 16th, 2020 (Honolulu Deadline Submission) will be reviewed for the Istanbul release except Guilin requirement left-overs
      • Missing Honolulu Impact View per Component and a lot of information to understand the requirements, company commitments etc. - Please use the Requirement Template
      • Missing company commitments, specially for non functional requirement (30 mins PTL practice might not cover all the needs)
      • REQ-428 - Is it aligned with the Modeling Subcommittee?
      • Request to adopt a phasing approach for the Use Cases to avoid large number of components impacted within a release
      • Automated Test Cases are required for the Use Cases - have you factorized this as part of your company's engagement?
      • EUAG priorities? No new use case but continuity of former use cases i.e. 5G SON, Network Slicing, CCVPN, CNF
  • ACTIONS - No later than Nov 12th, 2020:
    • Subcommittees to follow up with the respective requirement owners and ensure that the remaining information is provided 
    • How does the TSC want to proceed with the first 4 approved requirements?
    • Guilin left-overs - start to meet Requirement Subcommittee for review

5

RelEng/Infrastructure

  • Tickets- Open showstoppers:
  • Tickets- Waiting on Community:
  • Migration Status / Upcoming Changes

5

PTL Update



5

Subcommittee Update

Arch, Ctrl-Loop, Modeling, Seccom, Requirement

ARC Review Schedule for Honolulu

5

EUAG Update



5

TCC / ONAP Liaison Update



5

TAC Update



5

Task Force Update

CNF, Maintenance, ONAP Enterprise



10

TSC Activities and Deadlines

Proposal to cancel #AGREEDthe TSC meeting on Nov 26 due will be cancelled
 due to the Thanksgiving holiday in the U.S.

5

Upcoming Events

Linux Foundation
  • LFN Developer & Testing Forum - Feb 1 - 4 (tentative)
    • Awaiting final confirmation by the LFN TAC

Action Items

  •  Krzysztof Opasiakprovide overview of milestone requirements for new release process at  PTL call and Nov 19 TSC call
  •  David McBride set meeting for Tuesday,   to review feedback on schedule.  Include Chaker, Krzysztof, Seshu, Vijay, and Dan.