Agenda Items | Presented By | Time | Notes/Links | JIRA Tasks | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Dublin Release RC2 Follow-up Sign-Off? | 40 mins | Milestone Status
Release Details
JIRA Query - Remaining 526 Items status != Closed AND status != Done AND project != "Sandbox Project" AND project != CI-Management AND project != "ONAP TSC" and fixVersion = "Dublin Release" ORDER BY key ASC, priority DESC, updated DESC | aaf/authz | |||||||||||
Any Infrastructure Improvement/Plan | Linux Foundation | 5 mins | Global-jjb update - 11 of 29 projects complete!
Dockerhub migration - proposed start 2019-07-22
Contributor License Agreements (CLA)
Any LF showstopper Completed #76345: Please help release Usecase-UI repos for Dublin Release #76359: Need help with the info.Yaml change | |||||||||||
PTL Update - Integration | 10 mins | In ODL, for instance, during release time-frame a few folks are granted “Supercommitter” rights, empowering them with merge rights on all repos. That way, when version number changes, or bug fix validated but no one to merge, etc., these set of people can take care of merging the needed patches and getting the release forward. Given our current structure in ONAP, where the integration team as to “vouch” for the state of ONAP before its release, it could make sense having Integration’s committer given such right. Suggestion: Integration Committers - 1 in APAC, 1 in EMEA & 1 in NAR to cover all the time-zones Scope: Code and Documentation Successful Story with OOM Alexis/Brian will prepare a detailed proposition to be reviewed by TSC | Carried forward from May 30 | |||||||||||
PTL Update - Portal | 5 mins | Congratulations Lorraine Welch ! | ||||||||||||
Subcommittee Update - CVC | 15 mins | Alignment to El Alto
| Carried forward from May 30 | |||||||||||
Frankfurt Release | 10 min | Frankfurt Activity's plan proposal from M0 to M1 | Carried forward from May 30
| |||||||||||
TCC Update | TSC Activities and Deadlines | Congratulations to Alla Goldner being elected as our ONAP Strategic Planning Committee (SPC) representative | ||||||||||||
Incoming ONAP Events | 5 mins |
Any remaining open question?
|
...
- Yipan Deng to follow up on OPTFRA-512. Due
- Yipan Deng to follow up on vCPW w/ TOSCA. Due
- Benjamin Cheung to follow up on 5G PFN pre-onboarding. Due
- Scott Blandford to follow up on Scaleout / CDS at PTL meeting. Due
- Seshu Kumar Mudiganti to follow up on CCVPN. Due
- David Perez Caparros to follow up on BBS @ ptl meeting. Due
- Bin Yang to follow up on consistent ID cloud region at PTL meeting. Due
- Ciaran Johnston to follow up on SOL004. Due
- Yipan Deng to follow up on HPA sec. Due
- Alexis de Talhouët FREEMAN, BRIAN D to put together a formal proposal at next week's TSC meeting
- Former user (Deleted) Rerun tool and discard readonly repos from branch list
- Former user (Deleted) to put forward an email waiver vote for MUSIC
- cl664y@att.com will compile the information on which companies block SSH to gerrit
- Collect feedback about Frankfurt Activity's plan proposal from M0 to M1 (TSC-129)
- Adolfo Perez-Duran meet with SECCOM on a recommended version and work with PTLs
- El Alto M3 checklist improvements for the security questions. Paweł Pawlak
- (SECCOM): Review Vulnerabilities that require significant rework, architecture change as "TSC MUST Have" candidates for El Alto
- Brian, Jess, Paul) to create a timeline considering our ONAP release roadmap including steps required for the multi-arch pipeline
...