The following items are expected to be completed for the project to Pass the M4 Code Freeze Milestone.

M4 Release Code Freeze Milestone overview is available in wiki.



Usage

  1. Use the "Copy" option (available under the ..., top right of this page) to duplicate this template into your project wiki.

  2. Fill out the Yes/No column

  3. Provide link to evidence (when necessary)



Practice Area

Checkpoint

Yes/No

Evidences

How to?

Practice Area

Checkpoint

Yes/No

Evidences

How to?

Security

Has the Release Security/Vulnerability table been filled out in the   protected Security Vulnerabilities wiki space?

Yes

R4 APPC Security/Vulnerability - Full Content

PTL reviews the NexusIQ scans for their project repos and fills out   the vulnerability review table

Are all Defects of priority Highest and High in status "Closed" in Jira? (this includes the Jira for Critical and Severe NexusIQ findings)

Yes

All Jira tickets for vulnerability elimination are complete.

Complete Jira tickets

Did the project achieve the enablement of transport level encryption on all interfaces and the option of disabling transport level encryption?

No

Progress been tacking on APPC-1487: Implement recommended Protocols from security communutyClosed

APPC-1551: Use https for CDT communicationClosedCDT GUI has been migrated to https - which was done after M3.

APPC-1573: migrate https for ODL RestConfClosed ODL RestConf migrate to https

Do all containers run as a non-root user and is documentation available for those containers that must run as root in order to enable ONAP features?

Yes

APPC is running under odl: https://gerrit.onap.org/r/gitweb?p=ccsdk/distribution.git;a=blob;f=odlsli/odlsli-alpine/src/main/docker/Dockerfile;h=2719102e74315b9626931962fcda90c3b359cd2e;hb=4b054f9fab21f76992441e92069694d9f0cba0aa

Dgbuilder is running under dgbuilder: https://gerrit.onap.org/r/gitweb?p=ccsdk/distribution.git;a=blob;f=dgbuilder-docker/src/main/docker/Dockerfile;h=c1fd8dbde01deefce2dcfec6b71b5987ebe9e4cb;hb=4b054f9fab21f76992441e92069694d9f0cba0aa

CDT is running under cdt: https://gerrit.onap.org/r/gitweb?p=appc/deployment.git;a=blob;f=cdt/src/main/docker/Dockerfile;h=514ddba9d0768abeb33282926ce2a339a6177ca6;hb=d69066a2ed223fc5f525fcff520c5740736c5cb6

Ansible is running under ansible (https://gerrit.onap.org/r/gitweb?p=ccsdk/distribution.git;a=blob;f=ansible-server/src/main/Dockerfile;h=40de69e69888c9b797dfb0e1be48cba0da9e7a74;hb=4b054f9fab21f76992441e92069694d9f0cba0aa)

 https://wiki.onap.org/display/DW/Best+Practices

Provide the "% Achieved" on the CII Best Practices program.

Passing: 98%

Silver: 93%

https://bestpractices.coreinfrastructure.org/en/projects/1579



As documented in CII  Badging Program, teams have to fill out CII Best Practices

Product Management

Have all JIRA Stories supporting the release use case been implemented?

Yes

Change Management use case has been implemented/delivered for code. The rest of opened JIRAs are for testing and documentation

APPC-1442: Change Management Use Case: Distribute TrafficClosed

For each JIRA story that are implemented in the current release, you have to setup in JIRA the JIRA fixVersion="Dublin Release"

List the Stories that will not be implemented in this current Release.

N/A



For each JIRA story that will not be implemented in the current Release, you have to setup in JIRA the JIRA fixVersion="El Alto Release"

Are committed Sprint Backlog Stories been coded and marked as "Closed" in Jira?

Yes

Getting issues...



Are all tasks associated with committed Sprint Backlog Stories been marked as "Closed" in Jira?

Yes

Getting issues...



Is there any Critical and Severe level security vulnerabilities older than 60 days old in the third party libraries used within your project unaddressed?

Nexus-IQ classifies level as the following:

  • Critical is level 7 to 10

  • Severe is level 4 to 6

  • Moderate is level 1 to 3

which is complaint with CVSS V2.0 rating.

Yes

R4 APPC Security/Vulnerability - Full Content

Ensure the Nexus-IQ report from “Jenkins CLM” shows 0 critical security vulnerability. Open the Nexus-IQ report for the details on each repo.

Release Management

Have all issues pertaining to FOSS been addressed?

Yes





Have all findings from previous milestones been addressed?

N/A

No Findings

For M2 and M3 Milestones, ensure all findings have been closed.

Has the Project Team reviewed and understood the most recent license scan reports from the LF, for both (a) licenses within the codebase and (b) licenses for third-party build time dependencies?

Yes





For both (a) and (b), have all high priority non-Project Licenses been either removed or escalated as likely exception requests?

Yes





Development

Are all Defects of priority Highest and High in status "Closed" in Jira?

Yes

Provide link to JIRA issue (type bug) of priority Highest and High. 



Has the Platform Maturity Table been updated with implementation Status at M4?

Yes



For each Release, there is a Platform Maturity table created for PTLs to record their goals and achievement at M4 (Example: Casablanca Release Platform Maturity)

Has the project team reach the Automated Unit Test Code Coverage expectation? (Refer to artifacts available in Sonar)

Yes

83.8% (4/9/2019)

Sonar

Guidance on Code Coverage and Static Code Analysis

Tools: Sonar

Is there any binaries (jar, war, tar, gz, gzip, zip files) in Gerrit project repository?

No



Refer to CI Development Best Practices

Is there any pending commit request older than 36 hours in Gerrit?

No

However, there are some commits in Draft status - which are for R5.

Gerrit Query: status:open label:verified -is:draft -label:Code-Review=-1 AND -label:Code-Review=-2  AND is:mergeable age:1week

Are all the Jenkins jobs successfully passed (verify + merge jobs)?

Yes

https://jenkins.onap.org/view/appc/

https://jenkins.onap.org/view/Merge-Jobs/

Have all OOM Staging Healtcheck related to your project passed?

Yes





Are all snapshot binaries available in Nexus-staging?

Yes

Provide link to evidence



Do you have a clear plan to implement the Independent Versioning and Release Process by RC0?

Yes



Contact the upstream teams to make sure they will release their artifacts (in Nexus Release repo) so you can build by depending on these released artifacts by RC0.

Integration and Testing

Have 100% of Continuous System Integration Testing (CSIT) Use Cases been implemented successfully in Jenkins?

It should include at least 1 CSIT that will be run on

Lab-xxx-OOM-Daily Jenkins Job

Yes

All jobs pertaining to your project MUST pass



Is there a Docker images available for your project deliverable?

Yes

https://nexus3.onap.org/#browse/search=keyword%3DAPPC-image%20AND%20version%3D1.5.0-SNAPSHOT*



Has the project passed the Integration Sanity Tests?

No access for Grafana

APPC csit is all working.

https://jenkins.onap.org/view/appc/job/appc-master-csit-healthcheck/

Integration sanity tests in Dublin Release cover:

  • ONAP deployment

  • All components health check

  • VNF onboarding and service creation for vFW use case

  • Model distribution for vFW

  • vFW instantiation

  • vFW closed loop

  • vFW deletion

No test failure reported on http://onapci.org/grafana/d/8cGRqBOmz/daily-summary?orgId=1

No Integration Blocking Issue with no workaround: Dublin Release Integration Test Blocking Issues

Has the project code successfully passed the Daily Build process?

Yes

https://jenkins.onap.org/view/integration/ all passed that is what I am seeing.

Goal is to ensure the latest project commit has not broken the Integration Daily Build

Doc



Does the project have a plan to finalise and close all remaining JIRA Documentation tickets?





Yes

All JIRA ticket related to Documentation will be closed and finished by RC1

Jira Query

project != "Sandbox Project" AND project != "ONAP TSC" AND project != CI-Management AND (labels=Documentation OR project=Documentation) AND status != Closed ORDER BY fixVersion ASC, status DESC, priority DESC, updated DESC



Jira Query (Bugs Only)

project != "Sandbox Project" AND project != "ONAP TSC" AND project != CI-Management AND (labels = Documentation OR project = Documentation) AND issuetype= Bug AND  fixversion = "Dublin Release" AND status != Closed ORDER BY issuetype DESC, fixVersion ASC, status DESC, priority DESC, updated DESC

Does the project team have a plan to complete all the Release related documents by RC1?

Yes