CCSDK/SDNC Weekly Meeting - 2021-02-11

Agenda:

  1. ONAP project news:

    • RocketChat replaced by Slack (onapproject.slack.com)

  2. Guilin Maintenance Release status:

  3. Presentation: CCSDK/SDN-R impacts for the E2E Network Slicing use case in Honolulu

  4. Honolulu Release status

    • CCSDK and SDNC were both approved as passed M2 (Spec Freeze) milestone at special TSC meeting 1/25.  Release planning templates :

    • ODL Aluminum port complete, however:

      • Local testing succeeded, but dockers are not currently being built properly in master.  Fix is in progress.

    • Next project milestone is M3 - Feature Freeze:

      • TSC vote scheduled for Feb 25, 2021 

        • M3 criteria includes that all release builds must be complete and helm charts must be updated in OOM to deliver released dockers

        • To allow time for code reviews, release builds and OOM review, final code reviews for CCSDK and SDNC Honolulu should be submitted no later than Feb 12, 2021 

  5. Open Discussion