Date  

Meeting Logistics

DayTimeMeeting IDZoom LinkJoin by phone
Monday[sdc] Team ONAP3, Mon UTC 11:00 / China 19:00 / Eastern 06:00 / Pacific 03:00https://lists.onap.org/g/onap-meetings/calendarSee Groups.io calendar invite

See Groups.io Calendar Invite


Meeting Attendees


Agenda & Minutes

Review open action items from last week

AgendaMinutes (Draft to be updated during call)
Slides

High Priority Bugs


High priority defects :

 

type key summary assignee reporter priority status resolution created updated due
Loading...
Refresh


Open review

Kohn timeplan

Release Planning: Kohn


 

Kohn timeplan has been approved by TSC.

M0 was last Thursday 7th Apr

 

Kohn timeplan to be revised due to changes in Jakarta timeplan and holiday in some countries on 6th May . M1 (General requirement approved) proposed to be moved from 26th May to 9th June, M2 proposed to be moved to 30th June

 

Release plan updated: Release Planning: Kohn

M1 moved to 9th June. Release management tasks published: SDC-3992 - Getting issue details... STATUS

M2 moved to 14th July

 

M1 moved to 23rd June. M2 moved to 14th July

 

M2 scheduled for this Thursday 14th July. Tasks to complete: SDC-4068 - Getting issue details... STATUS

 

M2 postponed by one week to Thursday 21st July

 

M2 conditionally approved by TSC last Thursday

 

M3 scheduled for 1st September

 

M3 postponed one week to 8th September

 

M3 and M4 scheduled for this Thursday 22nd Sept

 

M3 passed last Thursday (22nd Sept)

M4 postponed to this Thursday (29th Sept). RC also pushed out one week to 27th Oct. Sign off date remains the same (10th Nov)

 

M4 postponed to today, Monday 3rd Oct

Latest Kohn functional build (1.11.9) merged into OOM https://gerrit.onap.org/r/c/oom/+/131325

Branch created for Kohn bug fixes. Creation of associated Jenkins jobs in review https://gerrit.onap.org/r/c/ci-management/+/131326)

 

M4 approved by TSC last Thursday 6th Oct

RC planned for Oct 27th

 

RC planned for this Thursday 27th Oct - tasks to be completed: SDC-4197 - Getting issue details... STATUS

 

Sign off planned for this Thursday 10th Nov, but expected to, slip 1-3 weeks due to ONE Summit & Thanksgiving.

SDC tasks for sign off: SDC-4234 - Getting issue details... STATUS


London timeplan

Draft time plan for London:

Release Planning: London

 

Timeplan for London approved by TSC last Thursday.

Kickoff scheduled for Oct 20th

 

London Kickoff was last Thursday. Next milestone M1 (global req. approval on 1st Dec)


London impacts

SDC-4239 - Getting issue details... STATUS

SDC-4240 - Getting issue details... STATUS

Continuation of support for TOSCA functions


Bugs

Open bugs: 37 (no change)


key summary type created updated due assignee reporter priority status resolution
Loading...
Refresh


Multi-tenancy

 

Documentation and code reviews to be shared when ready. Documentation to be added in SDC wiki, with readthedocs to be updated when implemented

 

Architecture committee have requested the proposed solution be presented 

 

Demo to be presented next week

Request for review sent to Architecture Committee, waiting for response

 

Architecture review tomorrow 

ONAPARC-753 - Getting issue details... STATUS

 

Arch Comm review took place last week. The proposed approach was acceptable to the architecture committee, however they recommended pairwise discussions with other components such as A&AI, SO, DCAE to align on an overall solution



Action Items

  •  


Slack Channel: #SDC on LFN ONAP.org Slack instance (onapproject.slack.com)


Recording


Chat