May
- #AGREED the TSC approves - REQ-396Getting issue details... STATUS and - REQ-399Getting issue details... STATUS as TSC best practices for Jakarta
- #AGREED the TSC approves moving the Istanbul release from M0 to M1 with the exceptions of REQ-396, REQ-399 (best practices) to be clarified by May 27th and remaining project tasks for DMaaP, VNFSDK, SDC & UUI to be completed prior the M2.
- Istanbul schedule proposal - M1 on May 20th, 2021 - #AGREED TSC approved the Istanbul release (v.7 https://wiki.onap.org/x/DiSLBQ)
April
- #AGREED the TSC approves the signoff of the Honolulu release with the public announcement to be made on May 11
TSC approves rename the "K" release from Kyoto to Kohn in honor of Dan Kohn https://lists.onap.org/g/onap-tsc-vote/message/1946
- #AGREED the TSC approves promoting - REQ-443Getting issue details... STATUS - REQ-439Getting issue details... STATUS and - REQ-760Getting issue details... STATUS to be Global Requirements and - REQ-441Getting issue details... STATUS to be a Best Practice beginning with Istanbul.
TSC approve federating the ONAP Jira instance with other LF Jira instances for cross ticket linking https://lists.onap.org/g/onap-tsc-vote/message/1945
- #AGREED TSC approved the new roadmap i.e. remaining RC1/RC2 + Sign-Off on April 22nd, 2021 - https://lists.onap.org/g/onap-tsc-vote/message/1943
- 2021 Mentorship Projects -3 ONAP submissions approved by TSC
- Portal is moved to "unmaintained" project in alignment with TSC decision on April 1st, 2021
- Feedback about CPS waiver regarding documentation of requested waiver (HTTP vs HTTPS) #AGREED approved by the TSC
- 2021 Mentorship Projects - ONAP Policy Enhancements #Agreed
TSC approves that the ONAP Community has met the RC0 Honolulu milestone - https://lists.onap.org/g/onap-tsc-vote/message/1941
- #AGREED If no contributors step forward the Portal project shall be moved to unmaintained status
- #AGREED LFN Mentorship proposal: "Externalizing ONAP DBs to a separate namespace"
- #DISAGREED TSC did not agree to freeze the scope
- #AGREED the TSC approves a waiver for UUI about https://gerrit.onap.org/r/c/oom/+/119844
March
TSC approves to grant Super Committer rights to finalize the Honolulu release. At the same time we have requested Kanagaraj to promote one of his active contributors: Insights - https://lists.onap.org/g/onap-tsc-vote/message/1938
- #AGREED the TSC will re-assess RC0/RC1 on March 29th, 2021 at the PTL meeting.
- #AGREED The TSC approves aligning RC0 with RC1 on March 25th
- #AGREED the TSC approves setting the Kickoff date of April 1 for the Istanbul release, keeping all other release milestones still TBD
- #AGREED The TSC approves ONAP being an early adopter of the "community [wide] metrics" Insights dashboard.
- #AGREED the TSC approves the process and workflow as described in Project State: Unmaintained with the provision that "Maintenance" be changed to "Unmaintained" globally.
- #AGREED the TSC approves slipping the date for Honolulu RC0 and all following milestones by 1 week (March 18) . The new release date for Honolulu will be April 8th.
- TSC approved our new DCAE committers: Joanna Jeremicz and Tomasz Wrobel
- TSC ratified Byung-Woo Jun, our new Architecture Subcommittee Vice-Chair
- #AGREED the TSC approves a TSC initiated PTL election for Portal
February
The TSC agreed to dedicate more time for strategic planning during weekly TSC meetings - David will e-mail weekly release update to the TSC, rather than providing an update during the TSC meeting itself. A link to the update will be included in the TSC meeting agenda. Exceptions will include milestone dates or if there are urgent issues related to release that require TSC engagement.
- #AGREED continue TSC 2.0 discussion to next week - move all other topic other than the actual M3 vote on Honolulu
- #AGREED TSC approves Super Committer rights during the Honolulu release to DMaaP PTL Fiachra Corcoran.
: TSC ratifies the results of the nominations as the 2021 Chair of the Architecture Subcommittee : Chaker Al-Hakim - Ratification of the 2021 Architecture Subcommittee Election
January
- #AGREED Measurement for active community members- current method is OK - merged changesets from Insights Leaderboard
- #AGREED Using Zoom's automated closed captioning and transcription for ONAP TSC meetings and attach the automated transcription to the meeting minutes
TSC 2021-01-25 (PTL Honolulu M2 Review)
- #AGREED the TSC approves Honolulu M2 as passed with exceptions that the projects must complete their release management tasks by Feb 2 EOD (except Architecture Review) for all projects except SDC & DMAAP. SDC & DMAAP close exceptions by Feb 9
: TSC ratifies the results of the nominations as the 2021 Chair and Vice-Chair of the Requirements Subcommittee respectively: Alla.Goldner (Chair) and Timo Perala (Vice-Chair)- Ratification of the 2021 Requirements Subcommittee Election
- #AGREED the TSC moves the M2 approval decision to Monday, Jan 25
- #AGREED The TSC agreed to the termination of the Control-Loop Subcommittee. These activities will be merged as part of Requirements and Architecture Subcommittees
- #AGREED TSC approves the Honolulu release as passing the M1 Milestone with any open M1 Jira items to be completed by 5pm pacific time on Jan. 20, 2021
TSC 2021-01-11 (PTL Honolulu M1 Review)
- #AGREED the list of global requirements are now frozen for Honolulu with REQ-438 - COMPLETION OF JAVA LANGUAGE UPDATE (v8 → v11) IN PROGRESS and REQ-437 - COMPLETION OF PYTHON LANGUAGE UPDATE (v2.7 → v3.8) IN PROGRESS
- #AGREED the list of approved best practices are now frozen for Honolulu with REQ-439 - CONTINUATION OF PACKAGES UPGRADES IN DIRECT DEPENDENCIES IN PROGRESS , REQ-442 - COMPLETION OF HELM MIGRATION (v2 → v3) IN PROGRESS and REQ-443 - CONTINUATION OF CII BADGING SCORE IMPROVEMENTS FOR SILVER LEVEL IN PROGRESS
- #AGREED - REQ-432Getting issue details... STATUS will remain a feature, developed at best effort. a new REQ-xx will be submitted as a POC to validate the implementation.Later on this new REQ-xx will be subject to GR approval (since this requirement can not be implemented for new code only and therefore approved best practice by default
- #AGREED The TSC approves - REQ-437Getting issue details... STATUS and - REQ-438Getting issue details... STATUS as Global Requirements beginning with the Honolulu release.
- #AGREED the TSC agrees to use the poll function built into groups.io for electronic voting