APPC Beijing Release Sign-Off

DRAFT PROPOSAL FOR COMMENTS

The following items are expected to be completed for the project to Pass  Release Sign-Off Milestone.

Release Sign-Off Milestone overview is available in wiki.



Usage

  1. Use the "Copy" and "Move" options (available under the ..., top right of this page) to duplicate this template into your project wiki.

  2. Fill out the Yes/No column

  3. Provide link to evidence (when necessary)

Practice Area

Checkpoint

Yes/No

Evidences

How to?

Practice Area

Checkpoint

Yes/No

Evidences

How to?

Product Management

Are committed Product Backlog Stories been coded and marked as "Done" in Jira?

Yes

Link to JIRA

APPC Beijing Jiras



Are all tasks associated with committed Product Backlog Stories been marked as "Done" in Jira?

Yes

Link to JIRA

APPC Beijing Jiras



Provide the project features list under the form of a bulleted list.

Yes

See Release notes



Summarize any functionalities that were planned at Release planning and not delivered at Release Sign-Off

Yes

This was done in earlier checkpoints to remove MariaDB from Beijing release



Release Management

Have all issues pertaining to FOSS been addressed?

Yes





Have all findings from previous milestones been addressed?

Yes

These were tracked as Risks and have been since closed.



Development

Are all the Jenkins jobs successfully passed (verify + merge jobs)?

Yes





Are all binaries available in Nexus Release repository?

Yes

https://nexus.onap.org/#view-repositories;releases~browsestorage



Are all Docker images available In Nexus?

Yes

https://nexus3.onap.org/#browse/browse:docker.release



Are the Java and Docker manifest updated with the same version as in Nexus Release repository?

Yes





Integration and Testing


Have all CSIT Use Cases (created by each project team) passed?

Yes

https://jenkins.onap.org/view/CSIT/

Goal is to incease our confidence the latest commit did not break the major functionality. Jenkins CSIT Jobs

Has the project code successfully passed the Daily Build process?

Yes

https://jenkins.onap.org/view/Daily-Jobs/

Goal is to ensure the latest project commit has not broken the Integration Daily Build 

Has the project done the integration testing with related dependent projects?

Yes





Documentation

Has your team contributed and completed work in the following documentations in ReadTheDocs:

  1. Release Notes

  2. Project Documentation

Yes

Provide Link to ReadTheDocs Release Notes

https://onap.readthedocs.io/en/beijing/submodules/appc.git/docs/release-notes.html

Provide Link to ReadTheDocs Project Documentation

https://onap.readthedocs.io/en/beijing/guides/onap-developer/developing/index.html#application-controller