1. Introduction

This is the integration test cases for OSAM use case.

2. Scope

The integration test case for OSAM use case, it includes VNF and PNF design from SDC, PNF registration, PNF activation, VNF instantiation and closed loop for VNFs

3.Terms, definitions and abbreviations

AbbreviationFull Name
PNFPhysical Network Function
VNFVirtual Network Function
GUIGraphic User Interface
GWGateway
SEBASDN-Enabled Broadband Access


4. Test Framework

TODO here: Add image to show test framework... can use architecture picture...


Module Introduction

ModuleFunction
OSAM CoreSeba specific operations are done on this VNF
OSAM GWAdapter between SEBA and OSAM Core
ONAPThe ONAP system for automation operation


5. Test Description

Test cases for ONAP, existing VF functions are going to be used for OSAM GW and OSAM Core. OSAM GW and OSAM Core specific designs should be applied also designed VFs should be deployed and their LCM should be managed as well.  ONAP's PNF functionally such as PNFD at onboarding time, PNF registration, PNF instantiation and PNF activation should be tested for SEBA.

5.1 Test Accounts

NameResponsibilityAccount
AdministratorResponsible for system management; Personnel permission configuration; ONAP external system registration; Operational life cycle managementdemo/demo123456!
DesignerService template designcs0008/demo123456!
TesterService template testjm0007/demo123456!
GovernorService template approvegv0001/demo123456!
OperatorService template distributionop0001/demo123456!


6. SDC Resource Design

6.1 OSAM Core Resource Design

Test NO:TEST-01
Project:SDC
Sub ProjectResource import for OSAM Core
Objective:Support to import the resources for OSAM
Operator:Designer, Tester
Pre-conditions:
  1. Required Tosca template should be ready for OSAM Core

Test Step:

  1. Designer logins to SDC portal.
  2. Creates certificates(Or reuse)
  3. Creates a new VSP
  4. Imports the TOSCA template which is prepared for OSAM Core, to VSP
  5. Imports the VSP to Catalogs as a VF Resource and sends for approval to a tester
  6. Tester logins to SDC portal and confirm the OSAM Core resource

The Result

  1. The OSAM Core resource is imported to catalog as a VF and ready for usage at a service design level.

Observation:

We can find a new resource for OSAM Core in SDC catalog.


6.2 OSAM GW Resource Design

Test NO:TEST-02
Project:SDC
Sub ProjectResource import for OSAM GW
Objective:Support to import the resource for OSAM
Operator:Designer, Tester
Pre-conditions:1.Required Tosca template should be ready for OSAM GW

Test Step:

  1. Designer logins to SDC portal.
  2. Creates certificates(Or reuse)
  3. Creates a new VSP
  4. Imports the TOSCA template which is prepared for OSAM GW, to VSP
  5. Imports the VSP to Catalogs as a VF Resource and sends for approval to a tester
  6. Tester logins to SDC portal and confirm the OSAM GW resource

The Result

  1. The OSAM GW resource is imported to catalog as a VF and ready for usage at a service design level.

Observation:

We can find a new resource for OSAM GW in SDC catalog.


6.3 SEBA Resource Design

Test NO:TEST-03
Project:SDC
Sub ProjectResource import for SEBA
Objective:Support to import the resource for OSAM
Operator:Designer, Tester
Pre-conditions:1. Required Tosca template should be ready for SEBA

Test Step:

  1. Designer logins to SDC portal.
  2. Creates certificates(Or reuse)
  3. Creates a new VSP
  4. Imports the TOSCA template which is prepared for SEBA, to VSP
  5. Imports the VSP to Catalogs as a PNF Resource and sends for approval to a tester
  6. Tester logins to SDC portal and confirm the SEBA resource

The Result

  1. The OSAM GW resource is imported to catalog as a PNF and ready for usage at a service design level.

Observation:

We can find a new resource for SEBA in SDC catalog.


7. SDC Service Design

7.1 OSAM Core Service Design

Test NO:TEST-04
Project:SDC
Sub Project:Design OSAM Core service
Objective:SDC support to design OSAM Core service
Pre-condition:
  1. OSAM Core resource must be cataloged as a VF

Test Step:

  1. Designer logins to SDC portal.
  2. Creates a new service from the catalog page
  3. Fill the required parameters such as category etc.
  4. Clicks composition and drags and drop the OSAM Core VF resource
  5. Saves the service and sends for testing to a tester user
  6. Tester logins to ONAP and approves the service template
  7. Governer logins to ONAP and approves the service template
  8. Operator logins to ONAP and distributes the service template

Test Result:

  1. The service must be cataloged for OSAM
  2. The service must be distributed to AAI, DCAE, APPC, SDNC and SO.

Observation:

1. We can find a new service for OSAM Core catalog in SDC

2. We can find a new service to instantiate in VID

7.2 OSAM GW Service Design

Test NO:TEST-05
Project:SDC
Sub Project:Design OSAM GW service
Objective:SDC support to design OSAM GW service
Pre-condition:
  1. OSAM GW resource must be cataloged as a VF

Test Step:

  1. Designer logins to SDC portal.
  2. Creates a new service from the catalog page
  3. Fill the required parameters such as category etc.
  4. Clicks composition and drags and drop the OSAM GW VF resource
  5. Saves the service and sends for testing to a tester user
  6. Tester logins to ONAP and approves the service template
  7. Governer logins to ONAP and approves the service template
  8. Operator logins to ONAP and distributes the service template

Test Result:

  1. The service must be cataloged for OSAM
  2. The service must be distributed to AAI, DCAE, APPC, SDNC and SO.

Observation:

1. We can find a new service for OSAM GW catalog in SDC

2. We can find a new service to instantiate in VID


7.3 SEBA Service Design

Test NO:TEST-06
Project:SDC
Sub Project:Design SEBA service
Objective:SDC support to design OSAM GW service