Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 25 Next »

The page is intended to summarize all the requirements for Guilin Release.

Candidate requirement proposals were frozen on May 28, 2020 TSC 2020-05-28

These requirements have been prioritized by the TSC to realistically fit within the Guilin Release on June 25th, 2020.

The Release Scope should be finalized during the M1 Release Planning milestone on July 9th, 2020

Note:  we will no longer be using a Confluence table to track requirements. More information here.

TSC Prioritization (Ranking)

  • RANK #0  – Special GO - quick wins, fully covered by involved companies
  • RANK #1 – TSC Must Have – Mandatory for the release
  • RANK #2 – Continuity  - Items continued from previous releases
  • RANK #3 – PTL Go – items that PTLs is OK to include since team has bandwidth
  • RANK #4 – NO GO OR Not yet Reviewed by TSC – items not approved for various reasons

T-Shirt Size

  • XS - <4 Man/Weeks;
  • S - ~6 Man/Weeks;
  • M - ~8 Man/Weeks;
  • L - ~12 Man/Weeks;
  • XL - > 12 Man/Weeks.

Milestone Scorecard (except M1)

  • Green: On Track
  • Yellow: Use Case/Requirement not on track but could be mitigated by reducing the current scope and/or fix this issue prior M4. Risks identified and documented under Frankfurt Risks  
  • Red: Use Case/Requirement not on track and issue identified that will prevent from completing the development by M4. Use Case/Requirement should be moved to POC in alignment with the POC definition or de-scoped from the Frankfurt release.

Guilin Use Cases

key summary assignee arch review tsc priority scope status t-shirt size m1 scorecard m1 approval m2/3 scorecard m2/3 approval m4 scorecard m4 approval
Loading...
Refresh

Guilin Requirements

key summary assignee arch review tsc priority scope status t-shirt size m1 scorecard m1 approval m2/3 scorecard m2/3 approval m4 scorecard m4 approval
Loading...
Refresh

Guilin Non-Functional Requirements

key summary assignee arch review tsc priority scope status t-shirt size m1 scorecard m1 approval m2/3 scorecard m2/3 approval m4 scorecard m4 approval
Loading...
Refresh

Guilin PoC

key summary assignee scope status t-shirt size
Loading...
Refresh


  • No labels